MCU16/0079 Appendix E - Traffic Impact Assessment
MOVEMENT SUMMARY
Site: 1 [2018 AM BG]
Intersection of Memorial Dive & Doonella Street
Roundabout
Movement Performance - Vehicles
Mov OD Demand Flows Deg. Average Level of 95% Back of Queue Prop. Effective Average
ID Mov Total HV Satn Delay Service Vehicles Distance Queued Stop Rate Speed
veh/h % v/c sec veh m per veh km/h
South: Memorial Drive (South)
1 L2 615 2.9 0.509 4.2 LOS A 4.7 33.4 0.22 0.47 54.3
2 T1 132 2.9 0.509 4.3 LOS A 4.7 33.4 0.22 0.47 55.5
3 R2 17 2.9 0.509 8.7 LOS A 4.7 33.4 0.22 0.47 55.3
3u U 9 2.9 0.509 10.7 LOS B 4.7 33.4 0.22 0.47 56.2
Approach 773 2.9 0.509 4.4 LOS A 4.7 33.4 0.22 0.47 54.5
East: Doonella Street (East)
4 L2 7 2.9 0.047 12.3 LOS B 0.3 2.2 0.88 0.77 48.7
5 T1 12 2.9 0.047 12.4 LOS B 0.3 2.2 0.88 0.77 49.7
6 R2 1 2.9 0.047 16.8 LOS B 0.3 2.2 0.88 0.77 49.5
6u U 1 2.9 0.047 18.8 LOS B 0.3 2.2 0.88 0.77 50.2
Approach 21 2.9 0.047 12.9 LOS B 0.3 2.2 0.88 0.77 49.4
North: Memorial Drive (North)
7 L2 6 2.9 0.295 11.6 LOS B 2.0 14.7 0.91 0.92 49.2
8 T1 123 2.9 0.295 11.7 LOS B 2.0 14.7 0.91 0.92 50.2
9 R2 15 2.9 0.295 16.1 LOS B 2.0 14.7 0.91 0.92 50.0
9u U 1 2.9 0.295 18.1 LOS B 2.0 14.7 0.91 0.92 50.7
Approach 145 2.9 0.295 12.2 LOS B 2.0 14.7 0.91 0.92 50.1
West: Doonella Street (West)
10 L2 15 2.9 0.725 5.8 LOS A 7.9 56.7 0.68 0.65 50.0
11 T1 21 2.9 0.725 5.9 LOS A 7.9 56.7 0.68 0.65 51.0
12 R2 864 2.9 0.725 10.4 LOS B 7.9 56.7 0.68 0.65 50.9
12u U 2 2.9 0.725 12.3 LOS B 7.9 56.7 0.68 0.65 51.6
Approach 902 2.9 0.725 10.2 LOS B 7.9 56.7 0.68 0.65 50.9
All Vehicles 1841 2.9 0.725 7.9 LOS A 7.9 56.7 0.51 0.60 52.2
Site Level of Service (LOS) Method: Delay (SIDRA). Site LOS Method is specified in the Parameter Settings dialog (Site tab).
Roundabout LOS Method: SIDRA Roundabout LOS.
Vehicle movement LOS values are based on average delay per movement.
Intersection and Approach LOS values are based on average delay for all vehicle movements.
Roundabout Capacity Model: SIDRA Standard.
SIDRA Standard Delay Model is used. Control Delay includes Geometric Delay.
Gap-Acceptance Capacity: SIDRA Standard (Akçelik M3D).
HV (%) values are calculated for All Movement Classes of All Heavy Vehicle Model Designation.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.