Council archive · source document
Negotiated Report (Representations made) MCU25 0118 (As Published) · MCU25/0118
Local Resource Separation Area (limited only to the north-
eastern corner of property)
Flood Hazard Overlay
Landslide Hazard Overlay
Assessment Type Representations made to original approval
1. BACKGROUND
A development approval for a Material Change of Use - Multiple dwelling was issued on 19
February 2026
The applicant suspended the appeal period and made representations on 16 March 2026 to the
development approval conditions. The representations are detailed below but primarily relate to
changes as a result further investigations having been undertaken (detailed design stage)
including:
- Utility services within the front setback and outside of the approved building footprint to
meet the relevant fire servicing requirements, and subsequent change to the approved
landscaped plans; and
- Item of clarity relating to the building height condition
At the time the application was publicly notified 53 properly made submissions were received. The
submitters were primarily concerned with works being undertaken relating to the subdivision of the
site and associated operational works, which is separate to the subject application.
2. ASSESSMENT
An assessment in relation to each of the submitted representations is provided below:
Existing Condition 4
Approved Plans
4. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the table below.
Plan No. Rev. Plan/Document Name Date
SK-4 G Site Sections, prepared by Hollindale 4 December
Mainwaring Architecture 2025
SK-6 G Material Selection, prepared by Hollindale 4 December
Mainwaring Architecture 2025
SK-7-0 G Ground Floor Plan, prepared by Hollindale 4 December
Mainwaring Architecture 2025
SK-7-1 G First Floor Plan, prepared by Hollindale 4 December
Mainwaring Architecture 2025
SK-7-2 G Second Floor Plan, prepared by Hollindale 4 December
Mainwaring Architecture 2025
SK7-3 G Roof Level, prepared by Hollindale 4 December
Mainwaring Architecture 2025
SK8-1 G Elevations, prepared by Hollindale 4 December
Mainwaring Architecture 2025
Page 2 of 11
Document Set ID: 24667136
Version: 3, Version Date: 25/04/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Negotiated Report (Representations made) MCU25 0118 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.9 MB (small file)
- File type
No other editions are linked here.