Negotiated Report (Representations made) MCU25 0118 (As Published) · MCU25/0118
determined as being a highly likely requirement. These services are shown in the images
provided at Figures 1 & 2 below.
In this regard, MRP have advised that the approved development requires a minimum fire
hydrant system pressure of 350 kPa at 20 L/s at the two most disadvantaged hydrant outlets
located on Level 2. Historic flow and pressure data for the Cooroy area indicate an available
street supply of approximately 390 kPa at 20 L/s. After accounting for pressure losses
through the required pipework, valves, fittings, and vertical rise of 9m+ through the building,
hydraulic modelling of the hydrant system from the Unitywater water main to the most
disadvantaged hydrants indicates the minimum required performance likely cannot be
achieved from the Unitywater water main supply alone. Accordingly, provision for a single
fire pump housed within a dedicated fire-rated pump room (3m x 5m x 2.1m high) is required
to supplement supply pressure and ensure compliance with the applicable fire services
standards. Importantly, this has been located clear of Council’s required 6.0m setback from
the frontage.
Given the need to introduce these utility structures, a suite of amended architectural and
landscape plans have been produced by Hollindale Mainwaring Architecture and Project
Page 4 of 11
Document Set ID: 24667136
Version: 3, Version Date: 25/04/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Negotiated Report (Representations made) MCU25 0118 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.9 MB (small file)
- File type
No other editions are linked here.