CSR Building Products Limited Page 49
West Ridge Quarry
Site Based Management Plan
Make sure emergency exit routes are kept open/unobstructed at all times.
Cover any dangerous goods spill with foam to prevent fumes from travelling to an
ignition source.
Maintain safe distance and monitor area to prevent anyone other than Emergency
Personnel from entering emergency area.
Disposal of any contaminated material shall be handled by Fire and Rescue Service
personnel.
Engage consultants for Site remediation and validation, if required.
Response That May Be Taken Contact the emergency services or regulatory authority if applicable.
In the Event of a Solid Spill:
Contain the spilled material and isolate the area.
Clean and reload material if possible.
Dispose of remaining material as appropriate.
Response that may be taken in the event of a Cyclone/Storm and/or Flood
General: Undertake a check and general clean-up of the Site.
In open areas, remove and dispose of all litter and waste material and ensure drains
and sumps are clean.
Remove all portable material and equipment that might become airborne to a suitable
building.
Remove all portable material and equipment that may be inundated by flooding to
high ground.
All non-portable materials and equipment to be secured and protected, as necessary.
Cyclone Watch (Distant Company operations continue as normal.
Cyclone) – Cyclone centre
The Site Manager to monitor the location and severity of cyclone and notify all staff of
is more than 24 hours
any relevant warnings.
predicted travelling time
from area: Check inspection of quarry area(s) and initiate further clean-up as required.
Cyclone Warning (Close Closely monitor location and severity of cyclone.
Cyclone) – Cyclone centre
Ensure battery operated radio is available on the premises to monitor reports.
is within 24 hours predicted
travelling time from the Check that all doors and windows in all buildings are securely closed.
area:
Fill any emergency generators with fuel.
Monitor progress of Site clean-up.
Relocate any moveable items indoors.
Cyclone Imminent – Monitor the situation and decide appropriate time to commence shut down of
Cyclone centre is within 12 operations.
hours travel of the area:
Clean-up completed and final inspection undertaken.
Ensure First Aid is accessible.
Non-essential personnel at their own request may leave the Site after a time
designated by the Site Manager.
Before vacating offices, all loose papers are to be placed in filing cabinets or draws.
Computer screens to be unplugged and placed on the floor facing an internal wall.
Computer equipment to be covered with plastic to prevent water damage.
December 2012 / file ref. 1271_610_001 GROUNDWORK p l u s
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.