iii. swales which are designed in accordance with the Water Sensitive
Urban Design Technical Design Guidelines for South East
Queensland
iv. have batters around the entire perimeter, or where demonstrated
that is not feasible, have retaining structures only of the maximum
size recommended within the Water by Design Technical Design
Guidelines for bio-retention basins.
35. All stormwater quality treatment devices must be maintained in accordance with
the Water by Design (2009) - Maintaining Vegetated Stormwater Assets
(Version 1). A copy of this document must be retained on the site together with
the approved Operational Works drawings for the stormwater quality treatment
system and a detailed life cycle costing of the system attached as an
addendum. Records of all maintenance activities undertaken must be kept and
made available to Council upon request.
36. Any proposed Community Management Statement required for the
development must include the Water by Design (2009) – Maintaining Vegetated
Stormwater Assets (Version 1) document and must include the full cost of
maintaining the system in accordance with that document.
37. The applicant must submit plans for approval with the operational works
application for the inclusion of educational signage or stencilling to be
incorporated within the development to ensure patrons are reminded to
minimise waste and place it in bins.
Stormwater Harvesting
38. Operating underground stormwater harvesting tanks must be provided for the
development. The tanks must be provided in accordance with an Operational
Works approval and must include in particular:
a. a total tank capacity of a size suitable to maintain expected non-potable
and outdoor uses for a 2 month period without rain.
b. a minimum catchment of 50% of the building roof area.
c. re-use of harvested rainwater for internal non-potable uses and outdoor
uses.
d. stormwater harvesting tanks are to be located to the rear of the building.
39. Certification must be submitted to Council from a qualified person which
certifies that the rainwater collection tank/s and associated reticulation has/have
been installed in accordance with the requirements of this Decision Notice.
Acid Sulfate Soils
40. All works must be carried out in accordance with an Acid Sulfate Soil and
Groundwater Management Plan for the development prepared by a suitably
qualified person and referenced in a Development Permit for Operational
Works. The Acid Sulfate Soil and Groundwater Management Plan submitted
with the application for Operational Works must detail:
a. Management necessary for the proposed filling to avoid any impacts of
the Potential Acid Sulfate Soils identified on the site – in particular
impacts related to compacting Acid Sulfate Soils into the groundwater
table and releasing water contaminants.
b. design measures necessary to prevent any oxidation of the potential acid
sulfate soils or transfer of acid sulfate soil leachates via dewatering of
groundwater through underground pipe bedding material.
Page 21 of 45
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.