Skip to the record
The gold standard in government transparency.

Council archive · source document

APPROVED Plans for Negotiated Decision Notice · 142009.1382

of 16

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Very large file (11.3 MB): may take a few minutes to open.

Log in to see the plans as drawn
 

    
   
  

a

oe BERM (300mm MIN HEIGHT)
RUN-OFF FROM PAD
DIRECTED TO SEDIMENT TRAP

UNBOUND PAVEMENT MATERIAL (GRAVEL) TO
GRADING 'B', TABLE 9 OF QUEENSLAND TRANSPORT
SPECIFICATION MRSS11.04 - EXCLUDE MATERIAL
FINER THAN AS SIEVE 2.36mm

TEMPORARY CONSTRUCTION ENTRY / EXIT
NOT TO SCALE

FORM U-SHAPED CREST TO ENSURE
oe OVER-TOPPING AT CENTRE OF DAM

GROUND LEVEL t NOMINAL 400mm HEIGHT
are — 1

 

LOOSE PLACE ROCK PITCHING
(NOMINAL STONE DIAMETER TO BE APPROX’ 150mm)

* NOMINAL 250mm DEPTH
TEMPORARY ROCK FILTER DAM - TYPICAL SECTION
NOT TO SCALE

3.0m MAX
SPILL THRU WEIR
3.0m MAX (IF REQUIRED) F42 GEOFABRIC
rs ae 7 FABRIC (TO AS 1304)

200
oil!
i

POSTS OR STEEL PICKETS
DRIVEN 600mm INTO

 

 

SEDIMENT FENCE
NOT TO SCALE GROUND

   

CONTOUR

Consulting Engineers §

  
   

2117 081 ew

DP Re me Fuge & Pee ned

030400 200

STORMWATER
RUN-OFF

4:2 12 =
ES rrr wee
. 16 TURF STRIP (1.0m WIDE). BALANCE OF

EXPOSED SURFACE TO BE TOPSOILED
AND GRASS SEEDED.

CUT-OFF DRAIN DETAILS
NOT TO SCALE

ND
GEOTEXTILE FABRIC TO TORS eUReee
BE SECURELY POSITIONED Line ater ey
UNDER GRATED LID AS

      
 

ALLOTMENT
PIT

PIT PROTECTION
NOT TO SCALE

 

   
 

 

Sunshine Coast Regional Council

Under no circumstances may the Plan & Specifications be departed
from within the written approval of Council.

PLANS APPROVED

Signature: ... ms
Delegat

 

 

5 APARTMENT DEVELOPMENT
AT 43-45 ELANDA ST, SUNSHINE BEACH
FOR OAK INVESTMENT HOLDINGS P/L

 

    
 

 

 

SEDIMENT & EROSION CONTROL

 

 

 

 

 

THE SITE FOREMAN 1ST

    
  
 
 

 

 

FREQUENCY SITE FOREMAN TO MONITOR PERFORMANCE AFTER
ev AVY DOWNEAL

 

DEADLINE

 

HE SITE f OREMAN |S RESF FORALL NSPECTION:

   

 

EUAN FA

 

 

 

 

EARTHWORKS NOTES

PUAN TITLE
EARTH WORKS, SEDIMENT AND
EROSION CONTROL DETAILS

 

 

       

SED IF OTHER OPTIONS ARE AVMARE
7 SEDIMEN] CONTROL FENCE

(A) NOT TOBE LOCATED IN ARE NTRATED FLOW

  
   
  
      
 

1 E OPERATIONA. PERIOD
GNIFICANT SEDIMENT RUNOFF IS HOT

0 4 0.0041 FOR DETAR S OF SEDMENT TRAPS

© BE PROVIDED WITH ON KERB DALET SEDMENT TRAP REFER

      
     

 

 

sHeeT @ of @

 

Used in these records

About this file

File size
11.3 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

APPROVED Plans for Negotiated Decision Notice.pdf · 11.3 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.