Stormwater Management Plan · MCU24/0153

of 38

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Very large file (15.9 MB): may take a few minutes to open.

Log in to see the plans as drawn

Original PDF page 12, section 1. The text section number identifies this passage in the reader.

        TABLE 6: POST-DEVELOPMENT UNMITIGATED CATCHMENT RUNOFF VALIDATION

          Catchment ID                    1% AEP Peak Flows (m³/s)                   Difference
                                    Rational Method     DRAINS Model
 Sub-catchment 1 (Roof 1 +
                                         0.0133                0.012                   -9.77%
 Driveway)
 Sub-catchment 2 (Roof 2 +
                                         0.0067                0.006                  -10.45%
 Walkway)
 Sub-catchment 3 (Roof 3 +
                                          0.009                0.008                  -11.11%
 Ramp)
 Sub-catchment 4 (Roof 4)                0.0138                0.012                  -13.04%
 Sub-catchment 5 (Walkway
                                         0.0034                0.003                  -11.76%
 Terrace)
 Sub-catchment 6 (pool deck
 Terrace)
                                         0.0207                0.017                  -17.84%
 Sub-catchment 7 (Garden
 Terrace 1)


For each catchment, the peak discharge calculated using the Rational Method was similar to the
value generated using the DRAINS model for the 1% AEP. Therefore, the modelling is considered to
be appropriately validated.

Flow Mitigation
Comparing the relevant post and pre-development flows highlights the requirement for the
developed case to be mitigated where it discharges into the legal point of discharge.

The DRAINS model was used to develop an adequately sized detention tank, ensuring that the post-
development flows are similar to the relevant pre-development flows.

It has been determined that the detention tank requires a minimum storage volume of 2.50 m³.
FIGURE 6 shows the Storage Volume graph for the critical 1% AEP event.

In addition to the detention tank, a rain harvesting tank is proposed as well. The rain harvesting tank
requires a minimum storage volume of 20 m³.




24083 – 51 Elanda Street, Sunshine Beach - SMP                                                  Page 12

Used in these records

About this file

File size
15.9 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Stormwater Management Plan.pdf · 15.9 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.