SERVICES & ORGANISATION COMMITTEE MEETING AGENDA                                  6 MARCH 2018


      Health and safety;
      Environment and sustainability;
      Contribution to local economy; and
      Price.

The submitted tendered price from Ri-con Contractors Pty Ltd at $444,227 excluding GST
represents a competitive price, together with their demonstrated ability to meet the non-price
criteria of the tender. Ri-con Contractors Pty Ltd demonstrated previous experience with
construction of similar projects, and they are a local Noosa business. In addition, they have the
necessary resources to meet Council’s contractual timeframes for practical completion.

The tender evaluation team considers this total tender submission to be the most advantageous to
Council and presents the best value for the limited amount of public funding.

3.      Programme & Next Steps

Pending Council approval, Ri-con Contractors Pty Ltd propose to construct the project within the
contractual timeframes which is between the 21 May 2018 and 3 August 2018. This window of
construction was stipulated by Council for two reasons:

A.      To minimise disruption to the patrons of Netanya Noosa Resort by undertaking the works
        during their planned renovation; and
B.      To avoid the Noosa Food and Wine Festival event which ends on the 20 May 2018.

4.      Construction Management & Inspections

Under the construct only delivery model, Council will maintain the overall project management role.
This will be supported by an externally appointed superintendent and specialist architectural and
engineering consultants to administer the contract and progressively inspect the works, ensuring
project deliverables are met.

Previous Council Consideration
Nil.

Finance
Council has allocated a total of $700,000 for this project with $500,000 allocated in the current
2017/2018 capital works budget. The total budget to construct the Main Beach boardwalk upgrade
is sufficient to complete the project as outlined below:

 Item                                                                                        Cost
 Costs to Date (up to January 2018)                                               $      69,236.00
 Tendered Contract Value                                                          $     444,227.00
 Superintendent                                                                   $      11,050.00
 Engineering Consultants                                                          $       1,500.00
 QLeave (on $444,227)                                                             $       2,110.08
 Sub-total                                                                        $     528,123.08
 Contingency                                                                      $      70,000.00
 Total                                                                            $     598,123.08
 Project Budget                                                                   $     700,000.00




                                                                                      Page 42 of 79
Log in to download the original file

2018-03-06 Services & Organisation Committee Agenda(PDF, 9MB).pdf · 9.3 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.