PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 25 MARCH 2014
As shown in Figure 5 below.
Figure 5 – Proposed Buffer to Lake Weyba
Extensive cut and fill earthworks are proposed, primarily to fill flood affected land to create
Precinct 2. Engineering plans indicate a total fill volume of roughly 149,000m 3, with the material
to be excavated primarily from a ridgeline adjacent the lake in Precinct 1 and from a number of
areas within Precinct 3. The plan below indicates the areas of cut (shown as warm colours) and
fill (shown as cool colours) and is included at A3 size as Attachment 3.
Figure 6 – Cut and Fill Plan
Page 91 of 231
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.