LANDSCAPING
25. The development site must be landscaped in accordance with Planning Scheme
Policy PSP 3 – Landscaping Plants and Guidelines and an Operational Works
approval and must include in particular:
any boundary fencing must be setback a minimum of 1m from the boundary
and/or covenant areas. The area of land between the boundary or covenant
areas and the fence must be densely landscaped to screen the fence from the
street. The landscaped area must include 1 feature tree every 3m;
dense landscaping must be provided along the southern boundary to effectively
screen the development from the adjoining residential dwellings;
dense landscaping must be planted for the full frontage of Val Crescent to
screen the development. The plantings must include a mix of low, medium and
tall shrubs and trees and in particular;
i. include 12 x 100 litre native tree species along the Val Crescent frontage
between the driveway and the southern boundary of the site. Proposed
species must be submitted for operational works approval;
shrubs and trees along the Goodchap Street frontage must have a minimum
pot size of 200mm and must include 5 feature trees with a pot size of 100 litres
1 feature tree each side of the porte cochere
provision of 1 street tree with a pot size of 100 litres for every 8 metres of
frontage
provide a survey plan prepared by a suitably qualified person which identifies
the mature trees on site and their possible retention in particular the trees near
the site boundaries.
the large eucalypt tree near the proposed driveway in Val Crescent must be
retained. In this regard, an arborist report outlining measures to maintain the
health of the tree during the design, construction and operational phase of the
development must be submitted for operational works approval
any vegetated water quality treatment system must be located to allow for
landscape screening of the development.
ENGINEERING
External Works
26. Goodchap Street and Val Crescent must be upgraded for the length of their frontage
to the subject site. The works must be undertaken in accordance with an Operational
Works approval and must include in particular:
reconstruction of any damaged kerb and channelling;
construction of pedestrian footpaths in accordance with the conditions of this
Decision Notice;
removal of the existing property accesses and reinstatement of the kerb,
footpath and verge area to match the balance of the site frontage, including the
provision of topsoil and turf where the existing verge is grassed;
relocation/reinstatement of existing on-street parking bays required as a result
of development works;
linemarking for any potential additional on street parking spaces.
This Condition is imposed pursuant to s665 of the Planning Act 2016 being non-trunk
infrastructure and s646 being necessary trunk infrastructure identified by Council’s
LGIP to service the development.
Page 24 of 52
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.