27. The existing formation in Val Crescent must be upgraded from the existing formation
in Goodchap Street and extending to the tangent point in the kerb line adjacent to the
northern boundary of No 3 Val Crescent. The works must be undertaken in
accordance with an Operational Works approval and must include but not be limited
to:
works designed and constructed in accordance with Council’s Planning
Scheme Policy PSP 5 – Engineering Design Standards – Roads, Drainage and
Earthworks (section 3.19(d) – Industrial/Commercial – Local road);
the full width of the formation in Val Crescent;
reinstatement of existing linemarking.
This Condition is imposed pursuant to s665 of the Planning Act 2016 being non-trunk
infrastructure and s646 being necessary trunk infrastructure identified by Council’s
LGIP to service the development.
Bus Stop relocation
28. The bus stop and associated infrastructure must be relocated in accordance with
Translink’s requirements. These works must also include the installation of a new
shelter in accordance with Council’s standard drawings. In this regard please note
that Council has a contract with a 3rd party to manufacture and install bus shelters.
The developer must:
carryout adjustment works to the kerb line and/or road linemarking along the
new bus stop bay as necessary to achieve compliance with the applicable
standards for cycle lanes requirements. The works must be included as part of
the Operational Works application.
liaise with the bus shelter manufacturer/installer and create all necessary
conditions for their works (i.e. concrete slab, etc.);
advise Council of timing for the installation of the bus shelter and report as soon
as possible any changes to the programme.
This condition is imposed pursuant to s646 of the Planning Act 2016 being necessary
trunk infrastructure identified by Council’s LGIP to service the development
29. Written approval from Translink’s Temporary Closures Team must be provided as
part of the Operational Works application, confirming that the application for impact to
the public transport bus network has been accepted and complies with DTMR’s
“Industry Guideline: A guide to managing public transport impacts”.
Site Access and Driveways
30. Sealed access driveways must be provided from Goodchap Street and Val Crescent
to all parking and manoeuvring areas of the development. The works must be
undertaken in accordance with an Operational Works approval and must include in
particular:
driveway crossovers generally in accordance with Council’s standard drawing
RS-051
suitable safety measures, including warning signage, to improve driver
awareness of pedestrians and enhance pedestrian safety. Warning signage
must be provided near the exit driveways to warn motorists of pedestrian
movement along the frontage street
Page 25 of 52
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.