07/2398 - SUPERSEDED Negotiated Decision Notice & copy sent to Referral Agencies [As Published] · 132007.2398

of 31

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

                                                                                         2007/2398




      Please note that these amounts are all subject to variations in the Consumer Price Index, All
      Groups Brisbane from December 2009 until the date of payment. All contributions must be
      paid prior to commencement of use.
General
92.   A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
      specifications for all engineering works that will become Council infrastructure, which shall be
      submitted in conjunction with an application for a Development Permit for Operational Works.
      In this regard a DXF/DWG file on GDA94 zone 56 grid of the proposed cadastre layout is to be
      submitted in conjunction with any application for Operational Works.
93.   Digital detailed designs including drawings, calculations, specifications and a schedule of
      works, shall be submitted with any application for a Development Permit for Operational Works
      in respect of roadworks and stormwater drainage works. The design shall be in accordance
      with Council’s Planning Scheme Policy PSP05 – Engineering Design Standards – Roads,
      Drainage and Earthworks. To avoid conflict with underground pipes or services, all existing
      and proposed services required by the development shall be shown on the plans.
94.   To facilitate production of As Constructed drawings it is suggested that all design drawings are
      submitted in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the
      use of ADAC are available at www.adac.com.au).
95.   A construction management plan/strategy shall be prepared by a suitably qualified Registered
      Professional Engineer and submitted to Council in conjunction with any application for
      Operational Works. The construction management plan shall ensure no damage occurs to
      Council services and that any adverse impact on the local area due to the construction works
      is within the acceptable limit and properly managed to the satisfaction of Council.
96.   A Traffic Management Plan for the each separate demolition and construction phase of the
      development shall be submitted to and approved by Council at least 5 working days prior to
      the commencement of any Demolition or Building works or at least 5 working days prior to the
      pre-start meeting for Operational Works. The Traffic Management Plan shall include but not
      be limited to:
      96.1   Mitigate any adverse impact and disturbance on the local residential area and on the
             traffic in the local and main roads to acceptable limits;
      96.2   Mitigate dust disturbance caused by vehicles and machinery movements;
      96.3   Limiting the routes for the heavy vehicles to the major road network and limit the use of
             the local roads within residential area as access to the site;
      96.4   Indicate provision for on-site and off-site parking for the required workforce;
      96.5   Indicate the location of loading and unloading areas;
      96.6   Indicate the location of any “holding” areas for heavy vehicles and
      96.7   Operating hours.
      It is be noted that the Elm Street frontage of site shall not be used for access, parking or
      loading and unloading during construction (and post construction) phase unless a specific
      written permit obtained from the Department of Main Roads.
97.   Any damage caused to any public utility during the course of construction shall be repaired to
      Council’s standards and at no cost to Council.
98.   Any alteration of any public utility or other facilities necessitated by the development of the
      land or associated construction works external to the site shall be at no cost to Council.
99.   The transportation of all materials to and from the site shall be undertaken in a manner such
      that no particle matter escapes onto a public road. All vehicles carrying materials either to or
      from the site shall be covered to prevent materials including dust being windblown from the
      vehicle.
                                                                                           12 of 31

Used in these records

About this file

File size
645 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

07_2398 - SUPERSEDED Negotiated Decision Notice & copy sent to Referral Agencies [As Published].pdf · 645 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.