07/2398 - SUPERSEDED Negotiated Decision Notice & copy sent to Referral Agencies [As Published] · 132007.2398
2007/2398
100. As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer
for design intent, and a Licensed Surveyor shall certify the cadastre and the location, level and
type of all services and structures. All of which shall be submitted to Council for checking and
for Council’s records.
The data must fully detail levels for all engineering works including but not limited to
roadworks, pathway, sewer main, water supply main, finished ground levels and pavement
surface levels and drainage structures that will become Council asset. The data shall be
submitted in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the
use of ADAC are available at www.adac.com.au).
Approval of works shall not be granted until all As Constructed information has been supplied
and accepted by Council.
Waste Management
101. A Waste Management Plan (Operational) generally in accordance with Planning Scheme
Policy No. 9 “Waste Management Multi-Dwellings and Commercial and Industrial Premises”,
must be submitted for the day-to-day operation of the development and approved by Council’s
Health Section prior to issue of development permit for operational works. The Waste
Management Plan (Operational) is to incorporate the following changes to the proposed
development:-
101.1 The proposed general waste bulk bin storage areas at the Aged Care Residence,
Apartment Building, Village Community Centre and temporary service to the
Independent Living Units whilst under construction, will require HRV 12.5m length travel
path and turning access.
101.2 If the waste storage area at the Aged Care Residence is not roofed, then the actual
bunded bin wash area is to be decreased in size to a maximum one square metre area.
101.3 The waste storage area at the Apartment Building is to be relocated to the western end
of the adjoining car parking spaces, to allow ease of access for collection and avoid the
unnecessary manoeuvring through this car park.
101.4 The waste storage areas at the Aged Care Residence, Apartment Building, Village
Community Centre and temporary service to the Independent Living Units whilst under
construction, each require their own separate bin wash facility.
101.5 Submit details for approval of the proposal for bin washing of the recycling bins located
at the service nodals.
101.6 Council will not provide a roadside collection service to the 80L and/or 120L general
waste wheelie bins at the Independent Living Units after their completion. The following
options must be considered including client costings, and an alternative proposed for
approval.
101.6.1 Option 1: Continue the temporary service of the bulk bins as a permanent
arrangement. This requires:
Details of the permanent waste storage area (location, size, bin wash,
etc).
HRV 12.5m length travel path and turning access for collection.
OR
Option 2: Provide a roadside collection service of 240L general waste wheelie
bins (one bin shared between two units). This requires:
10m vehicle length (not 9m as proposed) travel path and turning access
for collection.
Where possible bins are to be placed on one side of the road only to
prevent duplication of travel path and minimise service time and travel.
13 of 31
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
07/2398 - SUPERSEDED Negotiated Decision Notice & copy sent to Referral Agencies [As Published]Related documentApplication case desk ↗
About this file
- File size
- 645 KB (small file)
- File type
No other editions are linked here.