LONG TERM PLANNING FOR NOOSA SHIRE
No. Project Responsibility Update Status
1 Finalise Climate Change Adaptation Plan and initiate Director Environment & Sustainable Coastal Hazard Adaptation Plan (CHAP) risk assessment and cost benefit Behind Schedule @
implementation of actions Development analysis complete. Some earlier delays getting final phases complete
including updated hazard mapping. Draft CHAP now being prepared for
Council endorsment and community engagement. Broader whole of shire
Climate Change Response Plan scoped and background paper drafted.
Revised scope to be reported to Council in August.
2 ~ Implementation of Noosa Transport Strategy priority Director Infrastructure Services GoNoosa has been successfully implemented for the second year, this year Completed Q
actions as determined by Council incorporating a Loop Bus which has proved popular with local residents and
tourists. The Behaviour Change Program is being expanded to include more
schools and a community education program. Work is ongoing on other
public transport initiatives including electric buses, bus depot, and public
transport network improvements.
Go Noosa initiatives were cancelled for the Easter 2020 period due to COVID-
19. A draft MOU has been provided to TransLink and Kinetic (local bus
service provider) to investigate future opportunities for bus services in Noosa.
3 Investigate options for the future use of the former Director Corporate Services Options analysis completed. Note Council decided not to proceed with the Completed @
Tewantin TAFE site purchase at the July round of Council meetings.
4 Establish a Placemaking Team and commence pilot Director Environment & Sustainable Placemaking team to be established following the completion of the new Behind Schedule @
project Development Noosa Plan. Initial scoping work underway however delayed due to New
Noosa Plan not yet complete.
5 Finalise adoption of the new Noosa Planning Scheme Director Environment & Sustainable Minister for Planning signed off on New Noosa Plan in March subject to a On track Qo
Development number of conditions. Council could not consider the New Noosa Plan due to
Council elections (cartetaker provisions). New Noosa Plan was adopted by
the new Council at a July Special Meeting and is scheduled to commence on
31 July 2020.
6 Finalise cycleways and pathways studies to identify Director Infrastructure Services Shire Wide Walking & Cycling strategy - on track for completion in November. On track Qo
missing links High priority route - cycle corridor planning document - on track for completion
in September.
7 Continue implementation of Council's Revenue Director Corporate Services Working group formed and meetings underway. Meetings stalled due to Behind Schedule Oo
Diversification Project COVID-19 impacts on operations.
8 Finalise the Noosa Spit Shoreline Erosion Management Director Infrastructure Services The Noosa Shoreline Erosion Management Plan endorsed by Council. Completed Qo
Plan (SEMP) and develop an action plan to prioritise any Funding for implementation of the Noosa SEMP considered in the 2020/2021
recommendations arising from the SEMP budget.
Page 80 of 100See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.