Appendix E - Stormwater Management Plan · MCU12/0133

From the archive Development Application Part 2 of 2, 2 - Forms, Owner's Consent, Charitable Organisation Status, 3 - Town Planning Report (Noosa FLC), Appendix A - Code Ass Tables.,Appendix B - Proposal Plans.Appendix C - Archit Design Statement. File date in the archive: 2012-08-27 16:45.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
Bligh Tanner Consulting Engineers                                                                       Page 6
Noosa Flexi Learning Centre Stormwater Management Plan
August 2012



systems ensure water reuse             the reticulated water supply in
facilities have no impact on the       accordance with AS/NZS
quality of the town mains water.       3500:2003 Plumbing and
                                       Drainage.
Use of natural treatments and          S9.1 & S10.1 Development          The need for natural treatment
systems                                complies with the water quality   systems will be minimised by
O9 Natural treatment strategies,       standards in Table 2 of the SEQ   preserving the natural hydrology
including grass swales and bio-        Regional Plan Implementation      of the site, thereby minimising
retention systems, vegetated           Guideline No. 7                   any increase in surface runoff.
filtration strips and gross
pollutant traps, are used
wherever practicable;
AND
O10 Within the Shire Business
Centre, as shown on Map
SBC— where necessary,
drainage lines are ecologically
enhanced to ensure that the
water quality polishing functions
are of high standard.




As per Table 2 of the SEQ Regional Plan Implementation Guideline No. 7, development that
is less than 25% impervious is excluded from load-based objectives but is required to
capture and manage the first 10 mm of runoff per day from impervious areas.

The rationale for this, according to the SEQ Regional Plan Implementation Guideline No. 7 is

         “Since the load-based reductions are relative to the average pollutant loads in
         untreated runoff, a higher standard is effectively imposed on low-pollutant-generating
         development, by requiring pollutants to be removed to unachievable levels.
         Accordingly, development resulting in no more than six dwellings or 25%
         imperviousness or less can be addressed through simpler ‘deemed to comply’
         solutions


2.2 Hydrologic Objectives
The hydrologic objective for this site is to preserve the natural hydrologic regime of the
catchment by avoiding any increase in the volume of surface runoff leaving the site.

This would thereby satisfy the Frequent Flow Management Objective outlined in Table 4 of
the SEQ Regional Plan Implementation Guideline No. 7, which states that the first 10 m of
runoff should be captured and managed (where the total impervious surface is 0% to 40%)
management of captured stormwater may include infiltration to native soils (where adverse
impacts will not arise).


2.3 Water Savings Targets
The proposed centre is a Class 9 Commercial Building (under the Building Code of
Australia), and therefore the Queensland Development Code Mandatory Part 4.3 Alternative
Water Sources – Commercial Buildings applies.

Accordingly, the centre must have an alternate water source which provides water for
suitable uses.

Used in these records

About this file

File size
1.1 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Appendix E - Stormwater Management Plan.pdf · 1.1 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.