Stormwater Management Plan MCU17/0014
Original PDF page 10, section 1. The text section number identifies this passage in the reader.
BORNHORST + WARD | DOONELLA STREET UNITS
5.2.2 Source Nodes
The second step taken in creating the MUSIC models was to define ‘Source Nodes’ or Sub-Catchments.
The MUSIC model consisted of 5 source node types based on the proposed development layout and usage.
These nodes can be seen in figure 3: Proposed Treatment Train. Source node input parameters for each node
type were adopted in accordance with the MUSIC Modelled Guidelines.
5.3 TREATMENT METHODOLOGY
5.3.1 Treatment Nodes
The MUSIC model consisted of two treatment nodes as detailed in Table 5 and depicted in Figure 2. Treatment
node input parameters were based on the MUSIC Modelling Guidelines and sourced from the product supplier.
Table 3: Selected Stormwater Quality Treatment Devices
Treatment Device Discussion
Gross Pollutant Trap A gross pollutant trap is a treatment device designed to capture
EnvrioPod 200 coarse sediment, trash and vegetation matter in stormwater runoff. It
Stormwater360 is proposed to place an EnviroPod 200 at the start of the treatment
(or equivalent) train; ensuring ground runoff is filtered for gross pollutants before
entering the detention tank and reaching the filter cartridges.
Tertiary Treatment A Stormwater360 proprietary device containing Cartridge filtration
Device designed to remove nutrients and sediments from stormwater
6901 PSorb Cartidges runoff. It is proposed that 6x690mm PSorb Detention StormFilter
Stormwater360 cartridges are placed within the stormwater detention tank.
(or equivalent)
Refer to the Stormwater360 Plans and technical information attached in Appendix D for further details.
5.3.2 Proposed Treatment Train
A ‘Treatment Train’ was developed to target each of the pollutants of concern to be incorporated into the
development site layout. This treatment train is illustrated in Figure 3: Proposed Treatment Train.
Bornhorst + Ward Pty Ltd
Level 4, 67 Astor Terrace, Spring Hill, Qld 4000 Page 7
Ph. (07) 3013 4699 / [email protected]
A.B.N. 78 010 151 354
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Stormwater Management Plan MCU17_0014.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.