Stormwater Management Plan MCU17/0014
Original PDF page 9, section 1. The text section number identifies this passage in the reader.
BORNHORST + WARD | DOONELLA STREET UNITS
1) a material change of use for urban purposes that involves a land area greater than 2500 square
metres that:
a) will result in an impervious area greater than 25 per cent of the net developable area, or
b) will result in six or more dwellings, or
2) reconfiguring a lot for urban purposes that involves a land area greater than 2500 square metres
and will result in six or more lots, or
3) operational works for urban purposes that involve disturbing more than 2500 square metres of
land.
As the proposed development is for a material change of use that involves greater than 2500m2 of land, the
State Planning Policy requirements for water quality are applicable to the proposed development. As such,
stormwater quality treatment is proposed for development to ensure state requirements are achieved. The
effectiveness of the system at achieving water quality objectives was modelling using MUSIC.
5.1 POLLUTANTS OF CONCERN
The key pollutants to be targeted and the minimum reductions in mean annual loads described in the State
Planning Policy for the South East Queensland Region area outlined in Table 4.
Table 2: South East Queensland Water Quality Objectives
Pollutant Reduction in Mean Annual Load
Total Suspended Solids (TSS) 80%
Total Phosphorus (TP) 60%
Total Nitrogen (TN) 45%
Gross Pollutants (GP) 90%
5.2 MODELLING/ASSESSMENT APPROACH
A quantitative assessment of stormwater runoff quality was considered for the catchments ultimate developed
scenario.
The predicted reductions in mean annual loads of key pollutants have been identified using the “Model for
Urban Stormwater Improvement Conceptualisation” (MUSIC), Version 6 (6.1.0). MUSIC is a stormwater quality
modelling program that provides estimates of stormwater pollution generation and the performance of
stormwater management measures used in series or parallel to form a ‘treatment train’.
5.2.1 Meteorological Data
The first step in creating the MUSIC model was to select the appropriate meteorological data set (period and
time step) to be used as the basis for the runoff algorithms. Section 3.1 – Meteorological Data and Section 3.2
– Modelling Period and time-step, of the MUSC Modelling Guidelines details the Rainfall Data and Time Step
process requirements of the model, respectively.
The time step used for the MUSIC modelling process was: Tewantin RSL Park - 6 Minutes.
Bornhorst + Ward Pty Ltd
Level 4, 67 Astor Terrace, Spring Hill, Qld 4000 Page 6
Ph. (07) 3013 4699 / [email protected]
A.B.N. 78 010 151 354
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Stormwater Management Plan MCU17_0014.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.