Skip to the record
NoosaWatch™: The source of truth.

Original source · versioned page text

Appendix I - Stormwater Management Plan

Attached to the e-mail MCU14/0083 Appendices.

of 77

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
       3         Water Quality Management

       3.1       General

                 Water quality issues are associated with both the construction and operational
                 phases of the development.
                 Stormwater run-off will be managed and treated in accordance with the principles of
                 Water Sensitive Urban Design with the objective of improving stormwater quality by
                 removing nutrients, suspended solids and gross pollutants prior to discharge from the
                 development site.


       3.2       Temporary Water Quality Control

                 Temporary water quality control measures are required to control and filter the run-off
                 from areas disturbed during construction. These are typically erosion and sediment
                 control measures and should be the first items constructed when works begin. As
                 part of the construction drawing set, a construction Erosion and Sediment Control
                 Plan (ESCP) will be required to be generated. During the construction phase of the
                 development, an ESCP will be required to minimise the impacts upon water quality.
                 Construction disturbance and management of water release affected by acid sulphate
                 soils will also require consideration. An appropriate acid sulphate soil management
                 plan may be required to be developed and approved by the Department and
                 Environment and Heritage Protection (DEHP) prior to commencement of construction,
                 should investigation determine it is required.


       3.3       Permanent Water Quality Control

                 Permanent water control works are to be implemented to control run-off water quality
                 beyond the initial construction and maintenance stages. These control measures will
                 manage water quality control during the operational phase of the development and
                 have been designed to meet water quality objectives as described below.


       3.4       Water Quality Objectives

                 In accordance with the Urban Stormwater Quality Planning Guidelines (EHP, 2010),
                 design of treatment systems will aim to meet the following pollution load reduction
                 targets at the lawful point of discharge:
                      Total suspended solids reduction of 80% from an unmitigated development
                       case.
                      Total phosphorus reduction of 60% from an unmitigated development case.
                      Total nitrogen reduction of 45% from an unmitigated development case.



Mogpropmanagement Pty Ltd                         Page 4                                    205-002-002R
Stormwater Management Plan
Noosaville Site
Log in to download the original file

Appendix I - Stormwater Management Plan .pdf · 7.1 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.