Appendix I - Stormwater Management Plan
Attached to the e-mail MCU14/0083 Appendices.
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn Gross Pollutant reduction of 90% from an unmitigated development case.
3.5 Implementation
Water quality objective targets have been demonstrated to be met by implementing
treatments through stormwater detention/filtration systems located near the northern
boundary of the site and gross pollutant traps to reduce nutrient loadings, suspended
solids and gross pollutants.
A possible treatment train for the site has been developed based on the preliminary
drawing no. SK-02 Rev P5 by Michael Carr Architects, which outlines the proposed
site layout as shown on Figure 3.1 below. Drawing no. 205-002-C10.01 (refer
Appendix A) depicts the stormwater layout plan.
Figure 3.1 Proposed development layout
Mogpropmanagement Pty Ltd Page 5 205-002-002R
Stormwater Management Plan
Noosaville Site
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.