Delegated Report - Code - Planning 132004 4029 01 [As Published]
TOTAL $2,368
All headworks contributions must be paid prior to the issue of a Development Permit for
Operational Works.
Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should the
headworks contributions not be paid at the due time, Council shall call upon the trading bank
guarantee in full.
In the event that the Development Permit for Material Change of Use of Premises lapses or
is cancelled, the contribution or trading bank guarantee will be returned.
Erosion and Sediment Control
27. Any person acting on this permit shall prevent erosion and sediment export from leaving the
site. Site control measures such as silt fencing, controlled gravel access to the site and
controlled disposal of waste, will be necessary.
28. In this regard plans detailing the methods of controlling erosion and sediment are required
to be submitted to the Council for approval prior to obtaining a Development Permit for
Operational Works.
General
29. Any damage caused to any public utility during the course of construction shall be repaired
to Council’s standards and at no cost to Council.
30. Any alteration of any public utility or other facilities necessitated by the development of the
land or associated construction works external to the site shall be at no cost to Council.
31. The transportation of all materials to and from the site shall be undertaken in a manner such
that no particle matter escapes onto a public road. All vehicles carrying materials either to
or from the site shall be covered to prevent materials including dust being windblown from
the vehicle.
Building Services
32. A contour survey of the subject site is to be carried out by a Licensed Surveyor and is to be
submitted to Council at the time of application for building approval. Such survey shall set
out the natural surface levels of the site and the position of buildings on the site.
33. A verification survey of the building is to be carried out by a Licensed Surveyor and a
certificate lodged with Council at completion of the work confirming compliance with the
maximum building height above natural surface, required by the provisions of the Planning
Scheme.
Environmental Health
34. The developer must provide a suitably screened imperviously paved area large enough for
all refuse and recycling containers.
35. Swimming pool or spa pumps are to be contained in an acoustically treated enclosure or
located in a manner which prevents a noise nuisance beyond the subject land in accordance
with the nuisance provisions of the Environmental Protection Regulation 1998. On the spot
fines apply for such offences.
36. Noise emission from air conditioning equipment shall comply with the following requirements:
36.1. The equipment shall be installed and located in a manner which prevents noise
nuisance beyond the subject land in accordance with the nuisance provisions of the
Environmental Protection Regulation 1998 and Council’s Local Law No. 12 - Control of
Nuisances. Infringement Notices (on-the-spot fines) may apply for offences.
Page 17 of 22
Document Set ID: 22435870
22409127
Version: 1,
10,Version
VersionDate:
Date:23/05/2023
18/05/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.