GENERAL COMMITTEE MEETING AGENDA 15 JANUARY 2018
Finance
Council has allocated a total of $265,652 in the 2017/18 Capital Works budget for the Carbon
Reduction Plan (Building & Facilities).
This budget is sufficient for the design, installation and project management of the four solar
systems as outlined below:
Item Size of system Cost (excl. GST)
(KW)
Noosa Aquatic Centre 99.6 $93,891.05
Noosaville Depot 48.5 $51,981.29 Solar supply and installation,
net of Small Technology
The J 49.8 $51,981.29 Certificate rebates
The Leisure Centre 21.6 $22,262.62
ERM Power Management $33,017.45
Fee (15% of contracted Project management fee
solar price)
Total $253,133.70
Risks & Opportunities
Financial risks
The price of the Small Technology Certificates (STCs) reduces over the schedule of the
project. This is mitigated as the supplier has provided fixed lump sum pricing for the contract
which negates any impact of changes in pricing to the STCs.
Costs related to the network conditions with Energex. All costs associated with ensuring
zero export and grid connection costs with Energex have been included in the delivered cost.
Variation risks. The suppliers visited all sites, and recommended appropriately sized solar
systems for each site. This has been included in the lump sum price.
The performance of the solar systems is sub-optimal exposing the Council to on-going
electricity costs from the consumption of grid supplies electricity. This risk has been
mitigated as the supplier has offered a performance guarantee on output of 90% for 3 years.
The stated warranties for the equipment and installation are not supported. This risk is
minimal as ERM is responsible for all warranties under the contract.
Time risks
This project is not time critical, however significant delays will maintain the Council’s reliance
for the supply of 100% of its electricity from the grid, thereby delaying the expected savings
from generating its renewable energy.
Wet weather delays. The installation program has been developed based on the previous
experience of the supplier and has included contingency for weather.
Delays from unexpected site conditions such as roof or electrical deficiencies. This risk has
been minimised by suppliers visiting and inspecting each of the sites. A full structural
assessment will be undertaken on award of the contract.
Page 124 of 135
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.