Original source · versioned page text
Town Planning Assessment Report
function of, or access to Council
infrastructure.
Streetscape and effect on traffic AO13.1 AO13.1 - Complies
network Areas adjoining driveways Areas adjoining the driveway will
PO13 disturbed as a result of the not be disturbed.
The visual impact of driveways on driveway construction are grassed
the streetscape and surrounding or planted to minimise visual
area is minimised and significant impact and stabilise the soil.
adverse impacts on the traffic
network are avoided. AO13.2 AO13.2 - Complies
Vehicular access avoids
The dwelling will utilise an
disturbance to the tree protection
existing crossover to Upper
zone of trees on public land.
Pinbarren Creek Road and not
disturb vegetation.
Driveway Location AO14.1 AO14.1 - Complies
PO14 Only one driveway and crossover is
Only one driveway will be
Driveways and crossovers are provided.
provided.
located so they do not impede
the safe and efficient use of the AO14.2
road network. Where the premises AO14.2 – Not Applicable
has frontage to more than one
formed and sealed road and the
roads have differing orders in
the Road Hierarchy, the driveway
and cross-over is provided on
the frontage with the lower order.
AO14.3
For corner lots, driveways and AO14.3 – Not Applicable
crossovers are located in
accordance with Council's standard
drawings.
AO14.4 AO14.4 – Complies
If in the Rural zone or Rural The dwelling will utilise an
Residential zone, the driveway and existing crossover to Upper
cross-over is located to provide Pinbarren Creek Road.
minimum safe sight distances in
accordance with Austroads.
Bushfire Hazard Management AO15 AO15 - Complies
PO15 Within a bushfire hazard area
The building is located in a
Where located in a Bushfire where there is no reticulated water
medium potential bushfire area.
Hazard Area as shown on supply, the premises has:
The proposal complies with
the Bushfire Hazard Overlay a) an accessible dam, swimming
AO15 in that there are accessible
Map in Schedule 2 and not in a pool or water tank available
dams and water sources on the
water service area, an adequate, for firefighting purposes with
that have a volume exceeding
reliable, safely located and freely an onsite water volume of not
5000L.
accessible water supply is less than 5,000 litres; and
provided for fire fighting b) a water supply outlet pipe 50
purposes, which is in addition to millimetres in diameter and
day to day water supply. fitted with a standard fire
brigade fitting connected to
Page 14 of 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.