8. Engineering Report and Plans
The original of this document is very large (11.3 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Original PDF page 8, section 1. The text section number identifies this passage in the reader.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn ENGINEERING
VEGETATION CLEARING AND MANAGEMENT
There are no established trees or existing vegetation on the site. However, the existing concrete hardstand
and buildings will all be demolished and removed as part of the new development.
EARTHWORKS
The existing site conditions has a maximum elevation of approximately 11.5m AHD with a site grading of
around 4% across the development to the south west.
It is expected that some cutting of the property is required for stormwater management and standard vehicle
and pedestrian access to the proposed development.
These earthworks would be limited to the site bounds and to the volumes that would assist in allowing positive
fall to the drainage outlets as well as compliant vehicle access. These earthworks would be limited to the areas
shown in the proposed earthworks and cross-sectional designs of the development in plans 188-002-200 to
201 as part of Appendix A.
The designed earthworks will aim to reduce the amount of disturbance as much as possible while conforming
with accessibility, safety and ease of maintenance requirements. Any unsuitable spoil would be lawfully
removed from site.
All bulk earthworks within the development would be completed under Level 1 Geotechnical Supervision and
Australian Standard AS3798:2007 - Guidelines on earthworks for commercial and residential developments.
ROADWORKS/CARPARK CONSTRUCTION
The roadworks for the proposed development will consist of an entry and exit point from the existing David
Low Way frontage as well as the carpark within the property boundary. It is proposed that the access driveway
would be from the eastern boundary and provide service to the carpark only. Due to the separated lane design
of David Low Way, traffic access to the site is restricted from the south only. Vehicles are also limited to egress
to the north. This configuration supports in minimising conflict points for vehicles entering the traffic lane.
Page 8 of 13
2261 david low way, peregian beach, qld 4573 acn: 626 671 092 [email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.