Cover open earth/soil areas progressively (with concrete slabs and
pavements or mulch) to minimise areas of bare earth/soil.
Any stockpiles of excavated soil and demolition / construction waste must
be located where risk of erosion and sediment is minimal, and must be
protected from wind and water erosion.
Implement and maintain appropriate control measures such as catch drains and
sediment fences to prevent ponding of stormwater or discharge of stormwater
from the site to adjacent properties.
Provision of spill / pollution control equipment that is readily accessible to clean up
spills and leaks.
Ensure spill/pollution control measures are available and maintained in working
condition.
Sediment contained by the sediment control devices such as sandbags, sediment
fences and containment bunds must be frequently removed and placed in a
controlled area.
Implement an inspection schedule for any spill or leaks of any potential polluting
areas or activities.
5.5.4 Erosion Sediment Control Management Goals
Licenses, approvals, permits and inspection reports are in order.
Sediment or pollution control devices such as sandbags, sediment fences and containment
bunds are in place, maintained and effective.
Spill/ pollution control equipment is readily accessible at designated locations.
No accumulated sediment is contained by the sediment control devices such as hay bales,
sediment fences and containment bunds.
No sediment exceeding a depth of 300mm in the pollution control devices (e.g. silt trap).
5.5.5 Erosion and Sediment Control Implementation Program
Licenses, permits or approvals for each environmentally relevant activity must be obtained
prior to the commencement of the particular activity.
Appropriate control measures such as sediment fences, temporary construction entry/ exit
sediment traps, pollution containment devices (e.g. sandbags), stormwater diversion and
administrative controls must be installed and established prior to commencement of the
earthworks and construction activities.
Pollution control devices such as spill control equipment must be inspected on a regular
basis (at least weekly).
Other sediment and pollution control equipment such as containment bunds, hay bales and
sediment fences must be inspected on a regular basis (at least daily).
Inspection for any leaks, spills or potential contaminating activity must be performed on a
regular basis (at least daily).
Remove accumulated sediment or other contaminants from sediment/ pollution control
devices on a regular basis.
All erosion and sediment control measures must be inspected within 24 hours of expected
rain and within 18 hours of a rainfall event.
Excellence with Economy in Engineering 17
l:\7000-7999\7700-7799\7700\reports\18-07-19 stormwater management plan_issue d.docx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.