Attachment 13- Amended Flood Study MCU12/0208

of 130

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (37.1 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.

Original PDF page 23, section 1. The text section number identifies this passage in the reader.

Noosa on Weyba
Flood Study




6                      Existing Case Results
6.1                    Peak Water Levels
Figure 6 shows the existing case 100 year ARI peak water levels. It should be noted that this figure shows
the maximum extent of inundation from design events 1, 8, 9 and 10 and so includes all local and regional
flood events. The 100 year ARI peak water level with climate change is shown in Figure 12. The 10 and 2
year ARI peak water levels are shown in Figures 9 and 10 respectively.
The existing case peak water levels at the comparison points shown in Figure 4 are provided in Appendix F.
The 100 year ARI extent of inundation covers a significant portion of the Northbrook site, particularly the
western drainage channel which encompasses Keyser Creek. The existing case 100 year ARI local peak
flood levels in Keyser Creek within Lot 11 range from 2.09 to 2.17 mAHD. With the 20 year ARI storm surge
as a tailwater condition the 100 year ARI peak water level is between 2.16 and 2.23 mAHD. The 100 year
ARI regional peak flood levels range from 2.16 and 2.18 mAHD in this area. With the impact of climate
change the future 100 year ARI water levels in this area will be between 2.78 and 2.79 mAHD. Therefore
filling is required to ensure that the proposed lots in this area are not inundated.
The 100 year ARI peak flood levels within Eenie Creek and its tributaries also result from the 100 year ARI
local inflows combined with the 20 year ARI storm surge level. This demonstrates that storm surge events
dominate flood levels in the area.
The proposed development within the Hofmann site generally does not extend into areas which are
inundated in the 100 year ARI event, even with the impact of climate change. Only three lots in Precinct 3
Area I will require filling. These lots are located in an area that has existing levels of approximately 2.5
mAHD and above.
The existing case results demonstrated that the area around Lake Entrance Boulevard currently experiences
a significant amount of flooding. The second crossing of Lake Entrance Boulevard is un-trafficable during a
2 year ARI event, with a depth of flooding across the road of approximately 500mm. Access to the 70 lots
located to the south of this crossing is therefore restricted during a 2 year ARI event and above.
The existing Tidswell Road access track is also un-trafficable during a 5 year ARI event, which would prevent
access to the lot located to the south of Lot 11.
There are a few properties along Tidswell Road and Paradise Drive, located upstream of Lot 11, that are
currently inundated in local and regional flood events. It is therefore necessary to ensure that the proposed
development does not exacerbate these existing flooding issues.

6.2                    Peak Flows
The existing case peak flows at the comparison lines throughout the 2D section of the model shown in
Figure 4 are provided in Appendix G.

6.3                    Peak Velocities
The 100 year ARI peak velocities are shown in Figure 8. The existing case peak velocities at the
comparison points shown in Figure 4 are provided in Appendix H.
The peak velocities in the western drainage channel are quite low, with peak velocities typically around
0.2 m/s. The peak velocities in the tributary that drains through the J&K Hofmann site are typically around
0.5 m/s.




Northbrook Corporation Pty Ltd                   Version 4                                   16 September 2013
Flood Study v4 2.doc                       Commercial in Confidence                                   Page 18

Used in these records

About this file

File size
37.1 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 13- Amended Flood Study MCU12_0208.pdf · 37.1 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.