Attachment 13- Amended Flood Study MCU12/0208

of 130

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (37.1 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.

Original PDF page 26, section 1. The text section number identifies this passage in the reader.

Noosa on Weyba
Flood Study



Keyser Creek Crossing (Lot 11 Access Road)
This crossing of the creek will provide the only access to Precinct 1 and 2. It is proposed that this crossing
have 100 year ARI flood immunity (with climate change) and be trafficable during a PMF event. As the
regional PMF level is 4.23 mAHD the minimum possible road level is 3.83 mAHD. The culverts will consist of
3/3000 by 1500 RCBCs (upstream IL = 1.00 mAHD, downstream IL = 0.90 mAHD, length = 15.5m), 3/3000
by 1500 RCBCs (upstream IL = 1.10 mAHD, downstream IL = 1.00 mAHD, length = 15.5m), 1/2100 by 1500
RCBCs (upstream IL = 1.15 mAHD, downstream IL = 1.05 mAHD, length = 15.5m) and 1/1500 by 1500
RCBCs (upstream IL = 1.30 mAHD, downstream IL = 1.20 mAHD, length = 15.5m).
The entry and exit losses were assumed to be 0.4 and 0.7 as wingwalls between 30 and 70 degrees will be
utilised, and scour resistant outlet pad will be installed (refer Section 7.16.2 of QUDM). Debris deflector walls
will be installed on the inlets.
Swales will be required on the southern side of the crossing to ensure flows freely drain to the culverts.
Keyser Creek Pedestrian Crossing
A pedestrian and fire track will be provided along the northern boundary of Lot 11. The existing track will be
raised by around 400mm to a minimum level of 1.6 mAHD and 3/1500 by 600 RCBCs (upstream IL = 0.65
mAHD, downstream IL = 0.64 mAHD, length = 5m) will be provided underneath the road. The larger culvert
crossing will improve the tidal flushing in this area and the raised track will provide some attenuation of peak
flows. No flood immunity is required for this crossing.
Keyser Creek Tributary Crossing (Hollett Road East)
A crossing of this small tributary will be required to provide access to Precinct 1 and 2. The road level is
quite variable. It is proposed that this road have 50 year ARI flood immunity and be trafficable during a PMF
event.
Several culvert crossings are required. They consist of 1/2700 by 1200 RCBC (upstream IL = 4.00 mAHD,
downstream IL = 3.75 mAHD, length = 25m); 1/600 RCP (upstream IL = 4.00 mAHD, downstream IL = 3.60
mAHD, length = 25m); and 1/525 RCP (upstream IL = 4.70 mAHD, downstream IL = 4.50 mAHD, length =
25m). At other points along the road, underdrainage will be required for local overland flows.
This crossing is located to the north of the Noosa Wildlife Refuge. To allow for the safe passage of koalas
and other animals, between the Refuge and the environmental protection land on the subject site, the
minimum culvert height has been set at 1200mm, with a width of 2700mm. The Department of Main Roads
Fauna Sensitive Road Design (2000) indicates that culverts of this height have been known to allow for
passage of small, medium and large mammals, semi-arboreal mammals (which includes koalas), micro
chiropteran bats, reptiles, birds, amphibians and introduced predators.

7.3                  Proposed Stormwater Treatment
Numerous water sensitive urban design (WSUD) measures are proposed to treat stormwater. These include
bio-retention gardens and tree-pits located within the road reserve, vegetated swales, bio-retention swales,
bio-retention basins, litter baskets and rainwater tanks. For further details refer to the Stormwater
Management Plan (Cardno, September 2013). The proposed treatment measures will be located outside of
the 100 year ARI extent of inundation. The waterway corridor will not be utilised for stormwater treatment
purposes; stormwater will be treated to a sufficient level before it is discharged to this area.




Northbrook Corporation Pty Ltd                     Version 4                                    16 September 2013
Flood Study v4.doc                           Commercial in Confidence                                    Page 21

Used in these records

About this file

File size
37.1 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 13- Amended Flood Study MCU12_0208.pdf · 37.1 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.