Skip to the record
Accept no substitutions.

Council archive · source document

Attachment 13- Amended Flood Study MCU12/0208

of 130

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (37.1 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.

Original PDF page 9, section 1. The text section number identifies this passage in the reader.

Noosa on Weyba
Flood Study



The permanent waterbodies, as shown on aerial photography, of Eenie Creek and Keyser Creek were
manually defined in TUFLOW as minimum z shapes. This was necessary to reduce some triangulation
errors in the DEM which created false blockages across the waterway and created instabilities in the results.
Similarly other flow blockages in the tributaries, caused by triangulation errors, were removed by inserting
gully lines. The ALS data of the waterway does not penetrate the water surface, and so the storage and flow
capacity below this level is not included. This may result in an overestimation of the minor flood levels.
However, the impact is expected to be negligible for the major flood events.
The grid size used in TUFLOW was 5 metres. This is a grid size typical of urban areas and results in surface
levels at 2.5 metre intervals being used in the modelling.
For the developed case DTM, the earthworks model created in 12d was overlaid onto the existing surface
grid and re-exported.

3.2.3                  Roughness Values
The Manning’s n roughness values used in the 1D sections of Lake Weyba and Weyba Creek were kept at
the same values as those used in the Mike 11 modelling. The values varied at different sections but were
typically:
      n = 0.025 for waterway areas; and
      n = 0.10 for dense vegetation.
The Manning’s n roughness values used in the 2D grid were:
      n = 0.03 for waterway areas;
      n = 0.12 for dense vegetation;
      n = 0.20 for urban areas;
      n = 0.05 for grass areas with a few trees; and
      n = 0.04 for roadway crossings
A sensitivity analysis was conducted with a roughness value of 0.15 for dense vegetation areas. This
resulted in an increase in 100 year ARI peak water levels of around 100 to 150mm along Eenie Creek and
around 50mm along Keyser Creek. The impacts in Keyser Creek were not as great due to the low velocities
in this area.
The roughness values used in TUFLOW are shown in Figure 3.

3.2.4                  Model Inflows
The inflows into the TUFLOW model were taken from a WBNM model, which was compared to peak flows
using the Rational Method. The location of the inflows is shown in Figure 3. The TUFLOW inflows were
either inserted as 2D SA inflows, 2D boundary inflows or 1D inflows. The catchment delineation in the area
surrounding the site was different to that used in the regional flood modelling as there was insufficient detail
in the regional modelling. The developed case inflows were modified as required due to the increase in
impervious area and changes in catchment delineation. Further detail of the WBNM model is given in
Section 4.
For the climate change scenario, the inflows were increased by 20 percent to account for an intensification of
rainfall. This is the amount specified by the Inland Flooding Study (DERM, 2010) for the planning year 2090.

3.2.5                  Boundary Conditions
For local flood events the initial water level and tailwater level was set at Mean High Water Springs (MHWS)
as recommended by SCRC. The MHWS level at Munna Point, which is the closest permanent tidal datum, is
0.36 mAHD (Maritime Safety Queensland, 2012). This lower tailwater level ensures that the impact of
development is not drowned out. A sensitivity analysis was run using a tailwater level equal to Highest
Astronomical Tide (HAT) of 0.68 mAHD. This resulted in an increase in 100 year ARI peak water levels of
around 10mm, which was not considered significant.


Northbrook Corporation Pty Ltd                      Version 4                                  16 September 2013
Flood Study v4 2.doc                          Commercial in Confidence                                   Page 4

Used in these records

About this file

File size
37.1 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 13- Amended Flood Study MCU12_0208.pdf · 37.1 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.