2021-04-12 General Committee Meeting Minutes
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
GENERAL COMMITTEE MEETING MINUTES 12 APRIL 2021
a. The report must be amended to include specific reference to the
proposed on-site infiltration system and the proposed swale drain;
b. Certification that states that if the works are carried out in accordance
with the report the development of the site will not:
a. adversely impact on the stability of the subject site or
b. adversely impact on the stability of any adjoining land and/or
structure erected on the adjoining land
The report incorporating the above amendments must be resubmitted to
Council as part of any subsequent Development Permit for Operational
Works*.
*(Refer to Advisory Note)
40. Prior to the commencement of the use certification must be submitted to
Council from a qualified person* which certifies that the development has
been constructed in accordance with the approved Geotechnical Report for
the development and that the development will remain stable in the long
term.
*(Refer to advisory Note)
Earthworks and Retaining Walls
41. All earthworks must be undertaken in accordance with an Operational
Works approval, and contained entirely within the subject site unless
written permission from the respective landowner(s) is provided to Council.
42. All earthworks and associated retaining structures/batters/anchors must be
contained entirely within the subject site unless written permission from the
respective landowner(s) is provided to Council. All earthworks must be
undertaken in accordance with the provisions of Australian Standard
AS3798: Guidelines on Earthworks for Commercial and Residential
Developments.
43. Where the development involves excavation or filling over, or adjacent to,
drainage, water supply or sewerage infrastructure, all access chamber
surface levels must be adjusted to provide a freeboard of 100mm above
the finished ground surface level.
44. All retaining walls must be designed and constructed in accordance with
the planning scheme and must be certified by an RPEQ where exceeding
1.0m in height. All retaining walls that are publicly accessible and exceed
1.0m in height must be fitted with a commercial grade safety fence.
Damage to Services and Assets
45. Any damage caused to existing services and assets as a result of the
development works must be repaired at no cost to the asset owner at the
following times:
a. where the damage would cause a hazard to pedestrian or vehicle
safety, immediately; or
b. where otherwise, upon completion of the works associated with the
development.
Any repair work which proposes to alter the alignment or level of existing
services and assets must first be referred to the relevant service authority
for approval.
Page 8 of 16
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.