Pavement Design and Construction
22. Pavement design for privately owned works must be undertaken in accordance with
the relevant standards and be designed and constructed to comply with the Disability
Discrimination Act (DDA), Access to Premises Standard and relevant sections of
AS1428 Design for access and mobility. Structural integrity of the driveway and car
park areas will remain the responsibility of the property owner/developer and must be
certified by an RPEQ.
Works within Road Reserve and Reinstatement Works
23. Safe pedestrian access on all streets in the vicinity of the development must be
maintained at all times. Should footpath/road closures be necessary to carry out
construction works, Council’s Engineering Officer must be notified prior to the
proposed closure and all requirements complied with.
24. Where required, any reinstated road pavement must be in accordance with IPWEA
standard drawing RS-170 with road pavement resurfacing to consist of a minimum
depth of 50mm of an approved hot mixed asphaltic concrete.
Earthworks
25. All earthworks must be undertaken in accordance with the provisions of AS 3798
Guidelines on Earthworks for Commercial and Residential Development, with
geotechnical supervision and testing undertaken in accordance with Section 8 of the
Standard, and to a minimum of ‘Level 2’ as defined in Appendix B.
26. All Earthworks and construction works must be carried out taking into consideration
the protection of any existing above and below surface services, and the stability and
protection of fences and any buildings and structures on the adjoining properties.
Stormwater Drainage
27. Works associated with this permit must not adversely impact on the existing drainage
conditions on other properties including road and public footpath by blocking or
interfering with overland flow path.
28. Construction of all internal stormwater drainage works must comply with the relevant
section/s of Australian Standard AS/NZS 3500.3.
Erosion and Sediment Control
29. Sediment and erosion control measures must be in place prior to works commencing.
If such measures are not in place or are not satisfactory, “on the spot” fines may be
issued. Such fines can be issued if sediments from the site are found to enter or have
the potential to enter Council’s stormwater system, natural waterways, any
downstream stormwater filtration system or adversely impacting on other properties.
The sediment and erosion control design and measures have NOT been approved, it
is the site's Supervising Engineer who is responsible for ensuring that the sediment
and erosion control measures have:
a. Been duly designed by an RPEQ or CPESC and constructed in accordance
with "best practise" methods,
b. Been revised by an RPEQ or CPESC to address the issues raised by changes
in the projected construction schedule and/or methods,
c. Been revised to address predicted rainfall events, and
d. Achieve the desired environmental outcomes.
Council may request further controls to be installed should the implemented
measures be found inefficient.
Page 46 of 70
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.