                  column 1                                                 column 2
              Specific Outcomes                        Probable solutions (if code assessment)




                                                                                                                      Including amendments to 3 July 2017
                                                                                                          The Noosa Plan
                                                    AND
                                                    S1.2 Construction works are designed and
                                                    managed to restrict the extent of clearing and
                                                    soil exposure to that necessary for access, and
                                                    safe construction;
                                                    AND
                                                    S1.3 Clean stormwater is diverted or managed
                                                    around or through the site without increasing the
                                                    concentration of total suspended solids or other
                                                    contaminants in the flow and without causing
                                                    erosion (onsite or offsite);
                                                    AND
                                                    S1.4 Cleared areas are effectively stabilised
                                                    prior to rainfall if works are delayed or works are
                                                    not intended to occur immediately;
                                                    AND
                                                    S1.6 For buildings,
                                                    a)     upstream runoff must be diverted around
                                                           the construction site; and
                                                    b)     sediment barriers are provided downslope
                                                           of disturbed areas to prevent sediment
                                                           washing into gutters, drains and
                                                           watercourses either on or off the site; and
                                                    c)     exposed soil and construction access
                                                           must be managed in accordance with
                                                           International Erosion Control Association
                                                           Best Practice Erosion and Sediment
                                                           Control (BPESC) 2008; and
                                                    d)     temporary or permanent downpipes are
                                                           connected to the stormwater system
                                                           before laying the roof; or
                                                    e)     localised erosion is avoided by directing
                                                           flow from downpipes over non-erosive
                                                           areas.
O2 Works in a watercourse                           S2.1 Work within waterways must be
Construction activities within watercourses are     undertaken in accordance with Best Practice
planned to prevent erosion, construction failure    Erosion and Sediment Control, Appendix I –
and associated sedimentation.                       Instream works, Sections 14 and 16
                                                    International Erosion Control Association 2008.

                                                    S2.2 Temporary vehicular crossings of
                                                    waterways must be designed and constructed to
                                                    convey flows for the 50%AEP event and remain
                                                    stable for all rainfall events up to 10%AEP
                                                    event.




                                                14-131
                                   Erosion and Sediment Control Code

Used in these records

About this file

File size
9.9 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

2017-11-07 P&E Committee - Attachment 1 to Item 1 - Amendments for Multiple Housing Type 2 Duplex & Minor Corrections(PDF, 9MB).pdf · 9.9 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.