Civil Engineering Report

of 58

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Original PDF page 48, section 1. The text section number identifies this passage in the reader.

ROADS AND DRAINAGE CODE
Performance Criteria and Acceptable Solution
83 Butler Street, Tewantin
3 March 2022

              PERFORMANCE OUTCOMES                                              ACCEPTABLE OUTCOMES                                                     RESPONSE

                                                                  AND
                                                                  AO3.3                                                         RO3.3
c) minimise changes to the hydrological regime, including         Road infrastructure within or adjacent to native habitat      No new public roads are proposed to be constructed as part
drainage patterns, run-off and water quality;                     incorporates fences which allow for protected wildlife        of the development.
                                                                  movement and controls unrestricted access of domestic
d) avoid crossing watercourses, drainage lines and
                                                                  cats and dogs;
wetlands, but where such crossings are unavoidable,
disturbed areas are reinstated and revegetated on                 AND
completion of works; and
                                                                  AO3.4                                                         RO3.4
e) minimise bulk earthworks.                                      Native vegetation is protected from clearing or               Complies – Where applicable, native vegetation will be
                                                                  construction activities by—                                   protected from clearing or construction activities, as a
                                                                                                                                minimum, by-
                                                                  a) clearly marking vegetation to be retained with flagging
                                                                  tape;                                                         a) clearly marking vegetation to be retained with flagging
                                                                                                                                tape;
                                                                  b) installing protective fencing around the dripline of
                                                                  vegetation; and                                               b) installing protective fencing around the dripline of
                                                                                                                                vegetation; and
                                                                  c) ensuring stock piling, storage and vehicle parking occur
                                                                  outside the areas of vegetation to be retained;               c) ensuring stock piling, storage and vehicle parking occur
                                                                                                                                outside the areas of vegetation to be retained;
                                                                  AND

                                                                  AO3.5                                                         RO3.5
                                                                  Low impact construction techniques are used around            Complies – Where applicable, low impact construction
                                                                  areas of vegetation to be retained to minimise interference   techniques will be used around areas of vegetation to be
                                                                  with the vegetation.                                          retained to minimise interference with the vegetation.




l:\9000-9999\9200-9299\9279\code\03-03-22 roads and drainage code.docx
                                                                                            Page 4
Log in to download the original file

Civil Engineering Report.pdf · 4.9 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.