ORDINARY MEETING AGENDA 21 JANUARY 2021
Risks & Opportunities
Finance Risks Mitigation
Council request for scope increases. This is to be mitigated through Project Control
Group and Capital Works Executive management
and limitation of client requested scope variations.
Community requests for scope changes Council acceptance of scope as awarded with
once construction commences and project intention of not increasing scope.
becomes publicly visible.
Geotechnical conditions give rise for Pre-tender geotechnical investigations, and
contractor claiming variation costs. contract conditions have mitigated much of this
risk
Contractor claims for variations based on This has been mitigated through the lump sum
changes required for design. contract and a fully detailed design with further
mitigation to be managed through the
Superintendent and Project Control Group.
Clashes with underground services give rise The contract conditions require full investigations
for contractor claiming variation costs. by the contractor before proceeding with work.
Pre-tender “Dial before you dig” report on the
entire site has concluded that the likelihood of
clashes is mitigated. This report is part of the
tender documents.
Contingency amount being insufficient This project has a contingency at 5%and is to be
mitigated through a review of saving options and
strict variation control.
Programme Risks Mitigation
There is the potential that the project is The site is to be managed to minimise lost time
delayed due to above average wet weather from weather. The site is predominantly free
forecast. draining sand and generally lower risk of effects of
wet weather. The project has contingency
measures to mitigate knock on effects to other
stages.
Covid causes impacts to labour and It is assumed that construction industry will remain
materials an essential service and impacts are not forecast
into the programme,
Resource risk The project has no unusual or specialist
construction resource requirement and presents a
low risk to the contractor. The utilisation of
Council’s Superintendent and appointment of an
external Project manager consultant overseen by
Council’s Project Manager mitigates the
resourcing risk for Council.
Structure construction takes longer than The contractor is well resourced with an ability to
allowed for. increase crews to reduce risk of delays.
Safety Risks Mitigation
This is a medium to low-risk project due to Kane Constructions have extensive experience at
the working at heights up to 8 metres above this scale and type of project and would be
ground, with relatively flat topography and appointed as the Principal Contractor responsible
adequate space for normal construction for all Workplace Health and Safety of the site.
activities Prior to construction commencing, workplace
health and safety and pedestrian and traffic
management plans will be required to be
Page 15 of 26
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.