IDAS Code responses · OPW15/0240

Attached to the e-mail OPW15/0240 - Operational Works Application.

of 17

Text shows just the words. Original shows the document exactly as it was published.

_____________________________________________________________________________________________________________Callaghan and Toth Pty Ltd


                                                             in paragraph (a).
Infrastructure, including, access, parking, sewerage and water services
11.1 Prescribed tidal work has appropriate infrastructure, The infrastructure for prescribed tidal work is consistent with each         Complies – works will be undertaken in
including, in particular, road access, parking facilities,   relevant planning scheme standard.                                         accordance with a Construction management
sewerage services and water services, having regard                                                                                     plan which will detail requirements for traffic
to—                                                                                                                                     management, access and services.
(a) the nature and scale of the work; and
(b) the number of people that may be on or at the work
at any time; and
(c) the number of vehicles that may be on or moored at
the work at any time; and
(d) the protection of any foreshores near the work and
the vegetation and marine plants on the foreshores.
Design, construction and safety—all prescribed tidal work
12.1 Prescribed tidal work is designed and constructed       The design and construction of the prescribed tidal work is consistent     The sewer rising main has been designed in
in a way to ensure it is structurally sound, having regard   with the following standards—                                              accordance with relevant Australian Standards,
to the following—                                            (a) subject to paragraph (b), each Australian Standard relevant to the     Unitywater standards, SEQ Standards etc.
(a) relevant engineering standards;                          design or construction of structures, to the extent requirements stated
(b) the location of the work;                                in the Standard apply to the design or construction of prescribed tidal
(c) the purpose for which the work is to be used;            work;
(d) the impact of flooding, tidal influences and             (b) if a relevant planning scheme standard is more stringent than any
hydrodynamic changes                                         standard mentioned in paragraph
                                                             (a)—the relevant planning scheme standard, to the extent it is more
                                                             stringent than the standard mentioned in paragraph (a).
12.2 Prescribed tidal work does not adversely affect the     The design and construction of the prescribed tidal work is consistent     Complies – the works do not impact on any
structural integrity of any existing revetment or seawall or with the following standards—                                              seawall or another existing structure. The works
another existing structure.                                  (a) subject to paragraph (b), prescribed tidal work, including any shore   are mostly directionally drilled to reduce impacts.
                                                             abutment, piling or other structure connected with the work—
                                                               (i) does not place an additional load on any existing revetment or
                                                             seawall or another existing structure; or
                                                               (ii) can be structurally supported by an existing revetment or seawall
                                                             or another existing structure;
                                                             (b) if a relevant planning scheme standard is more stringent than the
                                                             standard mentioned in paragraph (a)—the relevant planning
                                                             scheme standard, to the extent it is more stringent
                                                             than the standard mentioned in paragraph (a).
12.3 Prescribed tidal work is designed and constructed       The design and construction of the prescribed tidal work is consistent     Complies – the works do not impact on the
in a way to ensure it does not adversely affect the          with the following standards—                                              stability of the bed and banks of any tidal water.



IDAS Code Responses_Rising Main Works_MossmanCourttoSerenityClose                                                                                                        pg. 6

Used in these records

About this file

File size
388 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

IDAS Code responses.pdf · 388 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.