AS PUBLISHED Information Request MCU24 0074 · MCU24/0074
30. Confirm the number of motorcycle parks to be provided on the ground floor carpark
adjacent to the Albert Street access. The GROUND PLAN DRAWING# 1004, ISSUE 2
prepared by Push Architecture annotates 5 spaces, however only 4 spaces have been
provided.
31. Demonstrate that a compliant aisle width can be maintained around the MRV loading bay
in accordance with Figure 2.2 AS/NSZ2890.1:2004.
32. Council is unsupportive of tandem carparks unless provided for staff carparking. Amend
basement carparking plans to designate tandem spaces for staff parking only or remove
spaces.
Issue – Waste & Servicing
33. Provide swept path manoeuvres to demonstrate that the waste collection arrangement for
6 Thomas Street (described as Lot 1 RP161212) is not compromised by the proposed
development. Include any changes to the existing access easements A, B, C & D if
required.
Note: Additional traffic assessment information may be required via a Further Advice to assess
the proposed carparking and servicing arrangements
Issue – Stormwater Quality
Council is generally supportive of the proposed stormwater quantity and quality strategy per
the Stormwater Management Plan (SMP) prepared by RECOR (Document Code 20230025-
SWMP01, Rev 1, Dated 30/5/24), however notes some additional information is required to
demonstrate the strategy has fully addressed the Performance Outcomes of the Water Quality
and Drainage Code. Provide additional information that addresses the following:
Information Required
34. Provide supporting stormwater quality modelling (e.g. MUSIC) that demonstrates the
proposed treatment train complies with the requirements of Performance Outcomes 1 &
6 of the Water Quality Drainage Code and achieves pollutant reduction targets of the
State Planning Policy 2017.
35. Provide Standard Drawings and SQUIDEP certification for all proposed proprietary
stormwater devices.
36. Amend the SMP to address Performance Outcome 2(a) of the Water Quality and
Drainage Code which requires the development to “incorporate allowance for increased
flood risk and tidal inundation through pipework as a result of climate change and sea
level rise”.
Note – Noosa Council adopt industry practice climate change allowance of 20% increase
to rainfall intensity and 800mm sea level rise.
Proprietary Stormwater Quality Devices (Applicant Information Only)
It is noted that additional conditions will be applied for private proprietary devices to ensure
maintenance responsibilities are upheld by the site owner/ management in accordance with
the manufacturer’s specifications. Documentation will be required to be provided to Council
prior to the commencement of the use from a Registered Professional Engineer (RPEQ)
specialising in stormwater design certifying that the stormwater management treatment train
as approved in the SMP and design drawings have been constructed in accordance with
engineering best practise and is functioning as designed.
Page 10 of 12
Document Set ID: 23083379
Version: 6, Version Date: 08/07/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
AS PUBLISHED Information Request MCU24 0074.pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.0 MB (small file)
- File type
No other editions are linked here.