Table 4 - Plant Species for temporary
Sowing Season Seed Mix
Autumn / Winter Oats @ 40kg/ha
Japanese millet @ 10kg/ha
Spring / Summer Oats @ 20kg/ha
Japanese millet @ 20kg/ha
3.4 SEDIMENT CONTROL
• Stockpiles will not be located within 5 metres of hazard areas, including likely areas of high velocity flows
such as waterways, paved areas and driveways.
• Sediment fences will:
Be installed where shown on the Erosion and Sediment Control Plans and elsewhere at the discretion
of the site superintendent to contain the coarser sediment fraction (including aggregate fines) as near
to as possible to the source
Have returns of 1 metre upslope at intervals along the fences where the catchment areas exceed
1,030 square metres, to limit the discharge reaching each section to 50 litres per second in a
maximum 10 year storm event.
• Sediment removed from any trapping device will be disposed in locations where further erosion and
consequent pollution to downstream lands and waterways will not occur.
• Water will be prevented from directly entering the permanent drainage system unless it is relatively
sediment free
• Temporary soil and water management structures will be removed only after the lands they are
protecting are stabilised.
3.5 WASTE MANAGEMENT
Acceptable bins will be provided for any concrete and mortar slurries, paints, acid washings, lightweight waste
materials and litter. Clearance services will be provided at least weekly.
4.0 CONSTRUCTION STAGING
4.1 INTRODUCTION
The construction staging outlines sediment and erosion control measures to be implemented within each
construction stage. Details of measures to be installed are also shown in the Erosion and Sediment Control plans
attached in Appendix B.
4.2 PHASE 1.1-SITE ESTABLISHMENT AND CLEARING
The first phase of construction will be site establishment including installation of all sediment fences, diversion
drains and all other sediment and erosion control measures as detailed in the Erosion and Sediment Control plans
attached in Appendix B. These works are to be undertaken prior to any disturbance or clearing of vegetation
other than works required for sediment and erosion control measures.
SOIL AND WATER MANAGEMENT PLAN - Revision A 71 Seav ew Terrace, Sun,hine Beach 5
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
2008/0169 Response to information request - 71 Seaview Tce Sunshine BeachRelated documentApplication case desk ↗
About this file
- File size
- 31.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.