Shake down devices are to be installed at site entries as detailed on the Erosion and Sediment Control plans.
On completion of site clearing, cleared vegetation is to be mulched and respread over all disturbed areas to
minimise erosion potential.
4.3 PHASE 1.2 - BULK EARTHWORKS
Phase 1.2 includes all bulk earthworks required for the construction of the dwelling and proposed driveways.
During the bulk earthworks stage, the entry roads to the subject site are to be swept daily and as directed by the
site supervisor.
4.4 PHASE 2.1 - STORMWATER DRAINAGE CONSTRUCTION
Energy dissipation at stormwater outlets is to be achieved via the placement of scattered rock at each outlet.
4.5 PHASE 3.1 - POST CONSTRUCTION
Removal of sediment and pollutants should be conducted in accordance with the Maroochy Shire Council
'Manual for Urban Erosion and Sediment Control', December 2007.
The removal of all unnecessary sediment and erosion control devises is to be undertaken as directed by the site
supervisor.
5.0 MAINTENANCE AND MONITORING
5.1 SITE INSPECTION AND MAINTENANCE
A self-auditing program will be established based on a Check Sheet as attached in Appendix C. A site inspection
using the Check Sheet will be made by the site supervisor:
• At least weekly
• Immediately before site closure
• Immediately following rainfall events greater than 5mm in any one 24 hour period.
The self audit will include:
• Recording the condition of every sediment control measure employed
• Recording maintenance requirements (if any) for each sediment control measure
• Recording the site where sediment is disposed
In addition, a suitably qualified person will be required to oversee the installation and maintenance of all soil and
water management works on site:
• Waste bins will be emptied as necessary. Disposal of waste will be in a manner approved by the Site
superintendent.
• Proper drainage of the site will be maintained. Inlet and outlet works will be checked to ensure they are
operating as intended.
SOIL AND WATER MANAGEMENT PLAN - Revision A /I Se.iviow Toi race, SunsI mc Beach 6
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
2008/0169 Response to information request - 71 Seaview Tce Sunshine BeachRelated documentApplication case desk ↗
About this file
- File size
- 31.0 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.