SUPERSEDED Decision Notice - Approved by Delegation of Authority - DBW25 0051 & OPW25 0054 (As Published) · OPW25/0054
DEMOLITION WORKS - CODES OF DEVELOPMENT
16. Unless specifically conditioned otherwise, all works must comply with the relevant acceptable
solutions as contained in the Waste Management Code and Water Quality and Drainage
Code of the Noosa Plan 2020.
Works
17. Demolition must be undertaken in a manner that causes no detrimental effect upon the
amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions
in accordance with the nuisance provisions of the Environmental Protection Act 1994.
Waste Management
18. Adequate area must be provided on-site for the collection and separate storage of recyclable,
non-recyclable, vegetative and hazardous materials in their specific waste streams during
removal or demolition works.
19. All waste materials must be removed from the site to avoid causing unhealthy conditions,
with the site left clean, tidy and free from any debris.
20. Where a development permit has not been issued for the future use of the site, hard surfaced
areas including concrete slabs must be removed and disturbed areas must be revegetated
in accordance with PSP2 Landscaping of the Noosa Plan 2020. Alternatively, the site must
be turfed within 20 business days of completing the removal or demolition work. Health and
Safety
21. All building materials containing asbestos, including asbestos cement sheeting or roofing and
lagging, are removed from the building prior to demolition or relocation.
22. Removal of building materials containing asbestos must be undertaken by a licensed
asbestos removalist.
23. Asbestos removal work (Section 466) of the Work Health and Safety Regulation 2011
requires a licensed asbestos removalist to give notice to Workplace Health and Safety
Queensland (WHSQ) of licensed asbestos removal work at least five days before the work
commences. Notification must be made using Form 65: Notification of licensed asbestos
removal work, demolition work or emergency demolition.
24. All building materials containing asbestos products are wrapped and disposed of in
accordance with the Public Health Regulation 2006 and the Environmental Protection
Regulation 2008. Note: Asbestos is a Regulated Waste. The Department of Environment &
Science licenses businesses that transport asbestos waste, and landfills that accept this
waste.
General
25. Infrastructure including reticulated water, sewerage, stormwater, and electricity must be
protected from damage and made safe to the standard required by the regulatory authority.
26. Any damage to footpaths, street plantings, natural vegetation/trees, kerb and channel,
bridges or roadways at the removal/demolition site must be repaired or reinstated to at least
pre-existing conditions.
Plumbing and Drainage
27. It is a requirement of the ‘Standard Plumbing and Drainage Regulation 2019’ that at
demolition of a building, the existing sanitary drain upstream from the connection point for a
service provider’s sewerage system must be sealed water tight. This work is deemed as
notifiable Work and must be carried out by a suitably licenced plumber who must submit an
As Constructed plan and Form 4 (Notifiable Works Form) to the QBCC (Queensland Building
Construction Commission) within 10 days of completing the work.
Page 4 of 12
Document Set ID: 23877592
Version: 5, Version Date: 10/07/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Decision Notice - Approved by Delegation of Authority - DBW25 0051 & OPW25 0054 (As Published)Related documentApplication case desk ↗
SUPERSEDED Decision Notice - Approved by Delegation of Authority - DBW25 0051 & OPW25 0054 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 196 KB (small file)
- File type
No other editions are linked here.