2007/2398
96.2 Mitigate dust disturbance caused by vehicles and machinery movements;
96.3 Limiting the routes for the heavy vehicles to the major road network and limit the use of
the local roads within residential area as access to the site;
96.4 Indicate provision for on-site and off-site parking for the required workforce;
96.5 Indicate the location of loading and unloading areas;
96.6 Indicate the location of any “holding” areas for heavy vehicles and
96.7 Operating hours.
It is be noted that the Elm Street frontage of site shall not be used for access, parking or
loading and unloading during construction (and post construction) phase unless a specific
written permit obtained from the Department of Main Roads.
97. Any damage caused to any public utility during the course of construction shall be repaired to
Council’s standards and at no cost to Council.
98. Any alteration of any public utility or other facilities necessitated by the development of the
land or associated construction works external to the site shall be at no cost to Council.
99. The transportation of all materials to and from the site shall be undertaken in a manner such
that no particle matter escapes onto a public road. All vehicles carrying materials either to or
from the site shall be covered to prevent materials including dust being windblown from the
vehicle.
100. As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer
for design intent, and a Licensed Surveyor shall certify the cadastre and the location, level and
type of all services and structures. All of which shall be submitted to Council for checking and
for Council’s records.
The data must fully detail levels for all engineering works including but not limited to
roadworks, pathway, sewer main, water supply main, finished ground levels and pavement
surface levels and drainage structures that will become Council asset. The data shall be
submitted in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the
use of ADAC are available at www.adac.com.au).
Approval of works shall not be granted until all As Constructed information has been supplied
and accepted by Council.
Waste Management
101. A Waste Management Plan (Operational) generally in accordance with Planning Scheme
Policy No. 9 “Waste Management Multi-Dwellings and Commercial and Industrial Premises”,
must be submitted for the day-to-day operation of the development and approved by Council’s
Health Section prior to issue of development permit for operational works. The Waste
Management Plan (Operational) is to incorporate the following changes to the proposed
development:-
101.1 The proposed general waste bulk bin storage areas at the Aged Care Residence,
Apartment Building, Village Community Centre and temporary service to the
Independent Living Units whilst under construction, will require HRV 12.5m length
travel path and turning access.
101.2 If the waste storage area at the Aged Care Residence is not roofed, then the actual
bunded bin wash area is to be decreased in size to a maximum one square metre
area.
101.3 The waste storage area at the Apartment Building is to be relocated to the western
end of the adjoining car parking spaces, to allow ease of access for collection and
avoid the unnecessary manoeuvring through this car park.
Page 13 of 32
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice plus copy sent to Referral Agencies [As Published]Related documentApplication case desk ↗
About this file
- File size
- 644 KB (small file)
- File type
No other editions are linked here.