ORDINARY MEETING MINUTES 17 DECEMBER 2020
DEMOLITION
Performance Bond
20. Security in the form of a cash bond or trading bank guarantee to the sum of $5,000
must be submitted to Council prior to the issue of a Development Permit for
Building Works for demolition, to secure the demolition conditions of this approval.
The cash bond or trading bank guarantee will be returned on performance of the
demolition conditions of this approval less any costs incurred by Council in respect
of enforcing performance of these demolition conditions. Council reserves the right
to call upon the bond or guaranteed sum to effect compliance with conditions.
Works
21. Demolition must be undertaken in a manner that causes no detrimental effect upon
the amenity of the neighbourhood by reason of the creation of excessive noise,
lighting, air-borne hazards, atmospheric pollutants (including dust or odours)
nuisance or any other emissions in accordance with the nuisance provisions of the
Environmental Protection Act 1994.
Waste management
22. A Waste Management Plan (demolition) must be submitted in accordance with
Planning Scheme Policy 11 - Waste Management Plan and approved by Council’s
Waste Coordinator prior to issue of a development permit for Building Works for
demolition, removal or relocation.
The purpose of the Waste Management Plan is to facilitate the segregation of
waste for the effective reuse and recycling of such materials. Segregated wastes
attract significantly reduced disposal fees at the landfill with some items free.
Higher gate fees are charged for mixed waste.
Waste storage areas must provide for adequate separation of all reusable,
recyclable and waste materials. These must be located so that they are convenient
and safe to use.
The Plan must contain the following information:
a. The areas for the storage and separation of waste shown on a site plan;
b. A waste management table as indicated below is to be completed showing
how waste material is to be segregated - recycled – reused or disposed; and
c. Table – Waste Management Table
MATERIALS ON-SITE DESTINATION
Re-use and Recycling Disposal
Expected waste Estimated On-site Off-site *specify
materials volume(m³) *specify *specify contractor and
proposed re- contractor and landfill site or
use or on- recycling other disposal
site recycling outlet site
methods
Excavation material
Green waste
Bricks
Concrete
Timber-please specify
Plasterboard
Metals - please
specify
Asbestos
Other - please specify
Note * If a demolition contractor is undertaking works, then the Waste Management
table is to be completed by the demolition contractor.
Page 13 of 25
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.