28. All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures
healthy, sustained and vigorous plant growth. All plant material must be allowed to
grow to full form and be refurbished when its life expectancy is reached.
29. All landscape works must be maintained generally in accordance with the approved
design for the life of the development.
ENVIRONMENTAL HEALTH
Underground tanks
30. Prior to the commencement of the use underground tanks shall be constructed and
installed in accordance with the following:
a. Tanks are to be made of fibre-reinforced thermosetting resin (fibreglass) that is
compatible with the product or tanks are to be made of a steel inner wall and a
fibre-reinforced thermosetting resin composite (fibreglass) outer wall.
b. Tanks are to be double-walled with an interstitial space.
c. Tanks are to meet the requirements of UL 1316 Glass fibre reinforced
underground storage tanks for petroleum products, alcohols and alcohol
gasoline mixtures, or the equivalent or tanks are to meet the requirements of
AS1692-2006 Steel tanks for flammable and combustible liquids, or the
equivalent.
d. Tanks are to have an overfill protection valve installed in the drop tube of the
tank. The overfill prevention valve shall be calibrated to prevent the tank from
being filled in excess of 90% of its capacity.
Submit certification
31. Prior to the commencement of the use certification by a suitably qualified person that
the underground tanks have been constructed and installed in accordance with the
above requirements must be submitted to Council.
Pipework
32. Prior to the commencement of the use pipework shall be constructed and installed in
compliance/accordance with the following:
a. Pipework is to be made of non-corrodible materials as defined by cl 1.4.37 AS
4897. The design, installation and operation of underground petroleum storage
systems.
b. Product piping is to be double-walled with an interstitial space.
c. Each tank fill point is to be clearly labelled and identified in accordance with AS
4977 Petroleum products - Pipeline, road tanker compartment and underground
tank identification.
d. Each tank fill point is to be fitted with a camlock type or other liquid-tight
connection.
e. Each tank fill point is to be provided with spill containment of at least 15 litre
capacity per spill point.
f. All fill and vapour recovery points are to be earthed in accordance with AS
1020.0 The control of undesirable static electricity and AS 3000 Electrical
installations.
Page 8 of 125
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.