Submit certification.
33. Prior to the commencement of the use certification by a suitably qualified person that
the pipework has been constructed and installed in accordance with the above
requirements must be submitted to Council.
Leak detection for underground tanks
34. Prior to the commencement of the use underground petroleum storage tanks shall be
monitored for leaks in accordance with the following:
a. Establish a statistical inventory analysis system that is rated to detect a release
of 0.76 litres/hour (or a release of 18 L/day), with greater than 95% confidence
(and less than 5% false positive) or install automatic tank gauging that is rated
to detect a release of 0.76 litres/hour (or a release of 18 L/day), with greater
than 95% confidence (and less than 5% false positive).
b. Install a tank pit observation well at the lowest point of each tank excavation pit.
Submit certification
35. Prior to the commencement of the use certification from a suitably qualified person
that the leak detection system was installed and was verified as meeting the above
leak detection performance standard using the current United States Environmental
Protection Agency (USEPA) protocol must be submitted to Council.
Leak detection for pipework
36. Prior to the commencement of the use product pipework shall be monitored for leaks
in accordance with the following:
a. Install electronic line leak detection for pressure piping that is rated to detect a
release of 0.76 litres/hour (or a release of 18 L/day), with greater than 95%
confidence (and less than 5% false positive); or
b. Install ‘safe suction’ design for suction piping in compliance with cl 4.3.4 AS
4897. The design, installation and operation of underground petroleum storage
systems.
Submit certification
37. Prior to the commencement of the use certification from a suitably qualified person
that the leak detection system was installed and was verified as meeting the above
leak detection performance standard using the current United States Environmental
Protection Agency (USEPA) protocol must be submitted to Council, or
38. Prior to the commencement of the use certification from a suitably qualified person
that the safe suction design has been installed and tested to comply with cl 4.3.4 AS
4897. The design, installation and operation of underground petroleum storage
systems must be submitted to Council.
Fuel dispensing areas
39. Prior to the commencement of the use fuel dispensing areas shall be constructed and
installed in accordance with the following:
a. All ground surfaces within the fuel dispensing area are to be constructed of
impermeable materials such as waterproofed, reinforced concrete that is free of
gaps and/or cracks. Impermeable, hydrocarbon resistant jointing material is to
be used between treated concrete slabs.
b. The fuel dispensing area is to be clearly demarcated from the uncovered
forecourt area, access roads, general parking bays and all other areas to
clearly delineate the higher contamination risk area from lower risk areas.
Page 9 of 125
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.