Original source · versioned page text
Planning Report
Attached to the e-mail MCU15/0068 Development Application for Material Change of Use.
Specific Outcomes Probable solutions Proposal
consequent pollution such as b) electric heat pump systems; or
greenhouse gas emissions. c) natural gas or LPG systems; or
d) any combination of a), b) or c).
Water supply and conservation S4.1 & S5.1 For a Class 1 building Not Applicable
O4 On-site water storage is designed other than a Detached house or The site is included within a reticulated
and operated to support the efficient Multiple Housing Type 1, outside a water area.
use of water; reticulated water service area, a
rainwater tank is to be installed with the
AND following minimum storage capacities—
a) Where no more than 3 bedrooms –
O5 On-site water storage is adequate 45,000 litres; or
for occupants every day use and fire b) Where more than 3 bedrooms –
fighting purposes. 60,000 litres;
AND
c) There is to be on the lot a dam,
swimming pool or water tank accessible
for use by the fire brigade that contains
at least 5,000 litres of water.
Advisory note
The 5,000 litres required can be included
within the water required in S4.2 or S5.1
providing it is accessible for the purpose of
fire fighting at all times and not used for other
domestic purposes.
Erosion and sediment control No solution provided. Complies
O6 Development does not cause erosion Appropriate erosion and sediment
or result in transport of sediments off- Advisory Note control measures will be applied to
site. Persons undertaking development, including ensure the development does not cause
building work, are required under the erosion or result in transport of
Environmental Protection (Water) Policy 1997
(EPP) to ensure that sediment and other
sediments off-site.
material including building waste, sawdust,
concrete, cement or paint are not deposited or
released into a roadside gutter, stormwater
drain or waterway, or into a place where it
could reasonably be expected to move or be
washed into a roadside gutter, stormwater
drain or waterway and are not washed from
the site. Council enforces the EPP and
penalties may apply.
Safety and security S7.1 The building entrance is clearly Complies
O7 For Multiple Housing Types 2, 3 identifiable and visible from the street, The proposed duplex achieves clearly
and 4, buildings and outdoor spaces are footpath and driveway; identifiable and visible entrance point
designed to protect the personal security from street.
and safety of residents by allowing for AND
natural surveillance.
S7.2 The internal path network has Complies
clear sightlines to the dwelling entry and A shared entrance point is proposed to
street access points; the lobby for access to each unit via
stairs or lift.
AND
S7.3 Visitors have direct access to the Complies
entrance without passing through Direct visitor access to the shared lobby
private outdoor living areas. on the ground floor is achieved without
passing through private outdoor living
areas.
Emergency access No solution provided. Not Applicable
O8 For Multiple housing Type 3, 4 & The proposal is for a Multiple Housing –
5, site design and layout ensures Type 2 Duplex development.
efficient access and egress for
emergency vehicles.
Basement drainage S9.1 Enclosed car parking and Not Applicable
O9 Buildings and access works are manoeuvring areas are constructed at a No basement proposed.
designed and sited to protect persons level that permits the parking area to
and property in the event of a flood and drain from the site by gravity means,
power failure. without the need for mechanical
pumping.
See the original