Attachment F - Previous Extension to Currency Period 3-11-20

of 8

Page text shows just the words. Original shows the document exactly as it was published.

      Pedestrian and Bicycle Facilities
8.    Pedestrian and bicycle facilities must be provided for the development. The works must be
      undertaken in accordance with an Operational Works approval and must include in particular
      a 2 metre wide footpath within the road verge extending from the end of the existing pathway
      in Gateway Drive to the northern boundary of proposed Lot 103. This condition is imposed
      pursuant to s665 of the Sustainable Planning Act 2009 being non-trunk infrastructure.
      Stormwater Drainage
9.    The site must be provided with a stormwater drainage system connecting to a lawful point of
      discharge. The works must be undertaken in accordance with an Operational Works
      approval and must include in particular:
      (a) A connection point for the future development of proposed Lot 103 to the existing
           stormwater drainage system
      (b) The retention of the existing overland flowpath that conveys stormwater runoff from the
           adjoining property (Lot 26 SP151406) through proposed Lot 103. The flows must be
           contained and conveyed wholly within a combined drainage solution consisting of
           underground drainage, capable of accommodating flows up to a Q10 event, and a
           landscaped and suitably stabilised (rock lined or other engineered alternative) open
           drain. The design of the drain must be sufficient to include all design storm events up
           to and including the 1%AEP event of critical duration. Design calculations (that include
           at a minimum depth of flow and velocity) and certification by a suitably qualified RPEQ
           demonstrating the above must be submitted as part of the operational works
           application
      (c) Additional elements in the design of the open drain (localised bunding etc) that allows
           stormwater flows from the minor storm event to enter the existing piped system and
           ensure that velocities (generated in both the major and minor events) are in accordance
           with the safety guidelines recommended in QUDM.
      Electricity and Telecommunication Services
10.   Underground reticulated electricity and telecommunication services must be provided to
      each lot in accordance with an approval for Operational Works and the standards and
      requirements of the relevant service provider.
11.   Unless otherwise stipulated by telecommunications legislation at the time of construction, the
      development must be provided with all necessary conduits, pits and pipes to accommodate
      the future connection of optic fibre technology telecommunications.
12.   Certification must be submitted to Council from all relevant service providers which certifies
      that the development has met the requirements of this Decision Notice and all applicable
      legislation at the time of construction.
      Easements
13.   A drainage easement must be created within proposed Lot 103. The easement must be:
      (a) Of sufficient width (approximately 4.5m) to encompass all elements of the combined
            underground pipe and open drain solution (underground pipe (Q10 flows), batters,
            bunds, etc. and a 1.5m maintenance track),
      (b) In favour of Lot 26 SP151406 to connect to a legal point of discharge as defined in
            QUDM.
      (c)   Alignment of the underground pipe, open drain, and easement is to be determined
            through operational works application (as per condition 9(b) above).
14.   A drainage easement must be created within proposed Lot 101. The easement must be:
      (a) In favour of Lot 26 SP151406 and proposed Lot 103,
      (b)   Centrally located over the existing piped drainage system connecting proposed Lot 103
            and Lot 26 SP151406 to the existing stormwater discharge point in Gateway Drive.



                                                                                       Page 3 of 8
Log in to download the original file

Attachment F - Previous Extension to Currency Period 3-11-20.pdf · 297 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.