Original source · versioned page text
Attachment F - Previous Extension to Currency Period 3-11-20
15. Unless otherwise agreed in writing by the relevant service provider, any public or third party
infrastructure located on the subject site must be placed within an easement registered
against the title of the property.
16. All easements must be designed in accordance with the planning scheme and granted at no
cost to the Grantee. Where the Grantee is Council or a service authority, the easement
documentation must be in accordance with the Grantee’s standard easement terms. Draft
easement documentation must be submitted to Council for endorsement.
17. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
18. All fill and associated batters must be undertaken in accordance with an Operational Works
approval, and contained entirely within the subject site unless written permission from the
respective landowner(s) is provided to Council.
19. All retaining walls must be designed and constructed in accordance with the planning scheme
and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
safety fence.
Damage to Services and Assets
20. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
(a) where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
(b) where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
UNITYWATER
Important Advisory Note - The following Unitywater conditions are applied in accordance with the
Chapter 4c, part 7 and sections 135 and 140(c) South East Queensland (Distribution and Retail)
Restructuring Act 2009 and Unitywater’s Interim Connections Policy. The conditions below form
part of a water connection aspect which are taken to be a water approval for a staged
connection. You are entitled to appeal against the water connection aspects of this application in
accordance with section 99BRAY and Chapter 4c, part 4, Divisions 1 and 2 of the South East
Queensland (Distribution and Retail) Restructuring Act 2009. Unitywater can be contacted as
follows:
Phone: 1300 0 Unity (1300 086 489)
Email: [email protected]
Web: www.unitywater.com
21. Reticulated water must be provided to each lot in the development. This must include:
(a) Ensuring that existing internal water pipes are wholly contained within the lot they will
serve.
(b) An approved water meter for each lot in accordance with Unitywater and SEQ Standard
Drawings.
(c) Provision of a water service to service proposed all lots in accordance with Unitywater
and SEQ Standard Drawings.
(d) Provision of a pipeline conduit under Gateway Drive in accordance with Unitywater and
SEQ Standard Drawings.
(e) An approved 150mm diameter water service connection to each lot in accordance with
Unitywater requirements.
Page 4 of 8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original