ORDINARY MEETING MINUTES 25 SEPTEMBER 2014
7. All works must be supervised by a Registered Professional Engineer of
Queensland (RPEQ) who is independent of the Developer and Principal
Contractor, and they must certify that all works conform to the Operational
Works permit. Where municipal works are involved, such confirmation must be
submitted for the respective hold points prior to any site inspection by Council
Officers.
8. All works must be constructed and work procedure undertaken in accordance
with:
a. The approved plans/documents and conditions detailed in this Decision
Notice
b. All relevant Noosa Council Planning Scheme Policies, standard drawings,
standard specifications and guidelines
c. The latest version of the Healthy Waterways document “Water Sensitive
Urban Design Technical Design Guidelines for South East Queensland”
for all water quality devices to be constructed on site
Works Within Road Reserve/Reinstatement
9. Safe pedestrian access on all streets in the vicinity of the development must be
maintained at all times. Should footpath/road closures be necessary to carry out
construction works, Council’s Engineering Officer must be notified prior to the
proposed closure and all requirements complied with.
10. All frontage works must match neatly with existing road and verge/footpath
features. Additional works beyond the frontage may be required to provide an
acceptable transition to existing road and verge/footpath profiles.
Pathways
11. All pathways must be constructed in accordance with the following
requirements:
a. All footpath/cycleway must comply with Council’s Standard Drawing SEQ
R-065.
b. All paths must have a slip resistant surface
c. Expansion and contraction joints must provide a flush finish. Installation of
joints by saw cutting is preferred to ensure a smooth ride for cyclists
d. The required work includes any modifications to ensure the footpath
finishes flush with all existing service covers and the like, or alternatively
these services are raised or altered, so as not to create a pedestrian
safety hazard
12. Pathways must:
a. terminate in a manner that ensures smooth transition to existing surfaces
for public safety
b. be designed and constructed to comply with the Disability Discrimination
Act (DDA), Access to Premises Standard, Austroads and relevant
sections of AS1428 Design for access and mobility
Site Access and Driveways
13. Any existing unnecessary or redundant property accesses must be removed,
and the kerb, footpath and verge area reinstated to match the existing footpath
and/or verge treatments. Grassed verge areas to be reinstated must be
provided with 100 mm topsoil and grass seed or turf, and must be maintained
by the developer until established.
Page 13 of 27
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.