Original source · versioned page text
Template4Waterwaybarrierworks_RosesRoad
Part 4 – CONSTRUCTING NEW OR MODIFYING (INCLUDING MAINTENANCE AND
REPLACEMENT) AN EXISTING WATERWAY BARRIER EXCEPT THOSE LISTED IN PARTS
2 AND 3
Note: If the development application involves more than one barrier relating to this part, please generate another part 4 and attach to the application.
Construction of a new barrier
17) What is the nature of the proposed
Maintenance of an existing barrier
work?
Replacement of an existing barrier
18) Briefly describe the proposed barrier.
19) If the barrier is temporary (in place less
than 12 months) how many days will the
barrier be in place?
20) Will the barrier extend across the Yes, complete question 20.1 and 20.2
waterway from bank to bank? No
20.1) What is the length of proposed
metres
barrier? (across the waterway)
20.2) What is the width of the waterway? metres
(bank to bank)
DA Form 1 – Template 4 Waterway barrier works
Version 1.1— 22 JUNE 2018
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original