planning report Other Change
AO5.4
Disposal of vegetative waste by
burning off is avoided.
Haulage activity and amenity No acceptable outcome provided
PO7
Haulage of material to and from a
site ensures—
(a) minimal disturbance to
neighbouring properties and
properties along the haulage
route; and
(b) Council’s road infrastructure
including pavements is not
adversely affected.
Extent of earthworks AO8
PO8 All earthworks, including cut and fill
The layout of the development batters, retaining walls and the like
provides adequate, clearly defined are contained within the subject site
and easily accessible—
(a) on-site vehicle parking and
manoeuvring areas; and
(b) loading and manoeuvring areas
for delivery and service vehicles.
Infrastructure protection No acceptable outcome provided
PO10
Earthworks and vehicular access do
not adversely impact on the capacity,
operations and maintenance of
existing infrastructure.
Environmental protection No acceptable outcome provided
PO11
Earthworks minimise any adverse
impact upon groundwater,
watercourses, drainage lines,
wetlands, and native vegetation.
Dams AO12.1 N/A
PO12 Where the site is in the Rural zone—
Dam location and construction
does not impact upon (a) the land has a slope of less than
neighbouring properties or road 25% (1:4);
reserves, in terms of— (b) the earthworks including cut and
fill batters and retaining walls are
(a) hydrology; setback a minimum of 50 metres
(b) alteration of existing overland from the property boundary; and
flow paths and patterns; (c) the size of the lot is greater than
(c) landslide or failure of dam wall; 5 hectares.
and
(d) effluent disposal areas. AO12.2
Where the site is in the Rural
residential zone or the Rural zone
and the lot is less than 5 hectares:
(a) the land has a slope of less than
1:6;
(b) the earthworks including cut and
fill batters and retaining walls are
setback a minimum of 20 metres
from the property boundary; and
(c) the dam work involves less than
500m³ of material.
AO12.3
For all other zones—
No acceptable outcome provided
Page 51 of 89
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (planning report Other Change.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.