Appendix J - Civil Engineering Report and SBSMP
Noosa Residential Development
Ref: 24553 C R002 REV03 10.08.21.docx
August 2021
7.4.1 Bioretention Basins
Catchment B1: A minimum 80m2 bioretention basin (area measured at surface area).
Catchment B2: A minimum 45m2 bioretention basin (area measured at surface area).
Bioretention basins remove contaminants and sedimentation from stormwater runoff via infiltration
through layers of soil media. The basin is made of a 400mm filter media layer and a 100mm transition
layer located above in-situ soil. The basin is to be vegetated by plants with root bases to suit the filter
depth, as per the landscape architect’s recommendations. These plants provide additional treatment
and will reduce the clogging of the basin. Runoff within the bioretention area gradually infiltrates the
soil layers, before discharging via sub surface drainage pipe. This pipe will discharge to the natural
surface with scour control as detailed in QUDM.
7.4.2 Swale drains
Grassed swales halt the movement of sediment lad runoff by slowing velocity and providing natural
filtration. As such, removing water pollutants and improving water quality to meet the required
treatment objectives mentioned in this report and ensure the prevention of sediment transportation.
Grass-lined swales are to be used across the development site to augment the bioretention basin.
A conceptual arrangement of the proposed grass line swales system can be seen in the ADG
Stormwater Quality Plan SK02 in Appendix C.
7.5 MUSIC Model
The sites stormwater run-off for the development was modelled using MUSIC (version 6.3.0) and the
water quality objectives for South East Queensland specified in the SPP 2017 of 80% TSS reduction,
60% TP reduction, 45% TN reduction, and 90% Gross Pollutants reduction.
The results shown in Figure 4 meet the percent reduction water quality objectives identified by Noosa
Shire Council standards and the SPP 2017.
Details of the MUSIC model are attached within Appendix I for further information.
Refer to Appendix C for the Preliminary Layout Plans prepared by this office.
BRISBANE / SYDNEY / MELBOURNE / GOLD COAST / SUNSHINE COAST / DARWIN / PERTH Page 18
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Appendix J - Civil Engineering Report and SBSMP.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.