Appendix J - Civil Engineering Report and SBSMP
Noosa Shire Council – The Noosa Plan 2020
Water Quality and Drainage Code
Performance Criteria and Acceptable Solutions
PERFORMANCE OUTCOMES ACCEPTABLE OUTCOMES COMMENTS
AO2.3 Development will comply, refer to
Stormwater flows discharging from the development are Stormwater Management Plan, in
demonstrated to be consistent with pre-development specific stormwater quantity
characteristics. section prepared by this office.
AO2.4 Development will comply, refer to
Development provides for the management of Stormwater Management Plan
stormwater to incorporate appropriate allowance for prepared by this office.
climate change impacts (including rainfall intensity and
sea level rise), in accordance in accordance with PSP6
Engineering Design Standards – Roads, Drainage and
Earthworks.
PO3 AO3.1 Development will comply, existing
Stormwater drainage infrastructure conveys run-off in a Stormwater drainage infrastructure meets the desired stormwater drainage infrastructure
manner that allows roads to deliver desired standards of standards of service for roads functionality set out in PSP6 considered in SBSMP won’t be
service appropriate to the local conditions and local Engineering Design Standards - Roads, Drainage and
stormwater drainage characteristics. negatively impacted by the
Earthworks.
development.
PO4 AO4.1 To be complied with at detailed
Stormwater infrastructure is compatible with existing The location, design and construction of stormwater design / construction stages
infrastructure, allows for easy access for the ongoing drainage structures is in accordance with PSP6 Engineering
Page 2 of 11
June 2021
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Appendix J - Civil Engineering Report and SBSMP.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.