Extension to Currency Period - Approved MCU21 0182 01 {As Published} · MCU21/0182.01
a. Civil engineering works;
b. Landscape works;
c. Erosion and sediment control works; and
d. Other relevant parties
39. A Construction Management Plan must be submitted to Council prior to the pre-start
meeting and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including:
i. A Traffic Management Control Plan in accordance with Manual of Uniform
Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
control measures prior to construction;
ii. Maintenance of safe pedestrian access across the frontage of the site both
during daily construction and after daily construction has ceased; and
iii. Proposed fencing to the site during the construction phase of the
development
b. Maintenance and protection of water quality and existing drainage lines through
the construction site through the implementation of appropriate erosion and
sediment control measures;
c. Include a post out to the local residents and businesses advising of the proposed
development, the expected time frames and the site contact details;
d. Include signage in prominent locations on the boundaries of the site advising of
the proposed development, the expected time frames and the site contact details;
40. Any changes to the details associated with the Principal Contractor during construction,
must be notified to council in writing within five business days of the change occurring.
41. Any conflict between the development and an existing or proposed service must be
referred to the relevant service authority for determination prior to commencement of
works.
Landscaping
42. Amended plans must be submitted to Council prior to the pre-start meeting and must
include the following:
42.1. Plant species selected for screening in particular along all boundary fences
including the street boundary must reach a minimum 4.6 metres at maturity. It is
noted for example Westringia ‘wynyabbie Gem’ reaches a height of 2 metres which
is not appropriate for use as a screening plant and has been included for use in
multiple sections of the boundaries for screening purposes on the Landscaping
Plan.
42.2. Details of the front landscaping garden including what is proposed being a 2 metre
wide landscaping garden along the frontage with no front fencing.
43. The development site must be landscaped. The works must be undertaken in
accordance with the Operational Works approval OPW21/0291 and the Noosa Plan for
that specific area and must include in particular:
a. the works shown on the Amended Plans submitted to Council;
b. landscaping to the north, east and southern boundaries must create a screen with
a minimum height of 4 – 6 metres;
c. provision of 2 street trees within the road reserve as detailed within the Approved
Plans and ensuring:
Document Set ID: 23016595
Version: 3, Version Date: 14/05/2024 Page 7 of 18
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Extension to Currency Period - Approved MCU21 0182 01 {As Published}.pdfRelated documentApplication case desk ↗
About this file
- File size
- 212 KB (small file)
- File type
No other editions are linked here.